Conditions or Reasons for Planning Application - CB/20/04383/DOC
Conditions or Reasons:
19) Prior to commencement of any development a Phase 2 investigation report for the entirety of the application site and a Remediation Method Statement should the Phase 2 report discover the need for remediation shall be submitted to and approved in writing by the Local Planning Authority. The development will thereafter be carried out in accordance with the approved details.

Reason: To ensure that any contamination associated with the site is adequately dealt with and mitigated in the interest of human health and the environment.

This condition is pre-commencement as it requires consideration of an assessment prior to any disturbance to the land prior to building works commencing on site.