| Conditions or Reasons: | 1)
The works shall begin not later than three years from the date of this consent.
Reason: To comply with Section 18 of the Planning (Listed Buildings and Conservation Areas) Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
2)
The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers: Roof Plan dated 25 5 21, LP1 dated 24 5 21, E1 dated 24 5 21, E2 dated 24 5 21, P1 dated 24 5 21, P2 dated 24 5 21, P3 dated 24 5 21, P4 dated 24 5 21, P5 dated 24 5 21.
Reason: To identify the approved plan/s and to avoid doubt. |
3)
None of the components, members or elements comprising the structural timber frame and fabric - including the infill panel material, stave or wattle & daub or brick, stone plaster - of the building shall be cut, damaged, altered or otherwise changed - other than those parts specifically identified within the submitted details. No sandblasting or another abrasive cleaning shall take place. Reason: To ensure that the special architectural or historic interest of the building or structure, its character and appearance is properly preserved, maintained and enhanced, in accordance with standard conservation good practice. (Section 16, NPPF)·Notwithstanding the approved plans, all new rainwater goods shall be of black painted[cast iron/aluminium] and shall be retained thereafter. Reason: To safeguard the special architectural and historic interest of this statutorily listed building. (Section 16, NPPF) |
4)
Before development/work begins and notwithstanding the details submitted with the application, details of the materials to be used for the external windows,doors, walls, roofs and rainwater goods of the proposed building/s shall be submitted to and approved in writing by the Local Planning Authority. The development/work shall be carried out only in accordance with the approved details. Reason: To ensure that the special historical and architectural interest and integrity of the listed building is conserved and maintained in accordance with Section 16 of the NPPF. |
5)
All new doors and windows shall be timber and detailed drawings at a scale of 1:10of all new doors and windows shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development. The works shall be carried out in strict accordance with the approved details. Reason: To ensure that the special historical and architectural interest and integrity of the listed building is conserved and maintained in accordance with Section 16 of the NPPF. |
|
|---|