Conditions or Reasons for Planning Application - CB/21/00477/DOC
Conditions or Reasons:
7) No development shall commence until a detailed surface water drainage scheme, to manage surface water runoff from the development for up to and including the 1 in 100 year event (+40%CC), and a maintenance and management plan for the scheme has been submitted to and approved in writing by the Local Planning Authority. The discharge rate shall be submitted and agreed as part of this drainage strategy. The final detailed design shall be based on the agreed drainage Strategy (Ref: Technical update note Sep2019 E3202/TN1/tjb/30092019 and FRA E3202-FRA-0317-Rev0 by Wormald Burrows and DEFRAs Non-statutory technical standards for sustainable drainage systems (March 2018) and shall be implemented and maintained as approved. Maintenance will ensure the system functions as designed for the lifetime of the development. Any variation to the connections and controls indicated on the approved drawing which may be necessary at the time of construction would require the resubmission of those details to the Local Planning Authority for approval.
The applicant should address the following points 1, 2, 3, and 4 when submitting details to discharge the condition:
Raingardens should be maximised to enhance the drainage, storage, general area and arrival where possible.
We will require full drainage drawings showing all connections, control features, storage, inverts etc. and how it communicates with the development wide scheme.
We expect the use of the SuDS management train, single point SuDS will be challenged. Where the use of permeable surfacing is proposed, this should be designed in accordance with the 'CIRIA RP992 The SuDS Manual Update: Paper RP992/28: Design Assessment Checklists for Permeable/Porous Pavement'. The addition of raingardens (drawing RDC 1125-102) is a welcome relief from the hard areas.
We expect the use of the SuDS management train, single point SuDS will be challenged. Where the use of permeable surfacing is proposed, this should be designed in accordance with the 'CIRIA RP992 The SuDS Manual Update: Paper RP992/28: Design Assessment Checklists for Permeable/Porous Pavement'. The addition of raingardens (drawing RDC 1125-102) is a welcome relief from the hard areas.
Reason: To ensure the approved system will function to a satisfactory minimum standard of operation and maintenance and prevent the increased risk of flooding both on and off site, in accordance with para 163 and 165 of the NPPF and its supporting technical guidance.
8) No building/dwelling shall be occupied until the developer has formally submitted in writing to the Local Planning Authority a finalised 'Maintenance and Management Plan' for the entire surface water drainage system, inclusive of any adoption arrangements and/or private ownership or responsibilities, and that the approved surface water drainage scheme has been correctly and fully installed as per the final approved details.
Reason: To ensure that the implementation and long term operation of a sustainable drainage system (SuDS) is in line with what has been approved, in accordance with Written Statement HCWS161, 18th December 2014.
21) Prior to the commencement of works a scheme of measures to provide for the provision of single yellow lines, up to 50m either side of the new access on Ivel Road and opposite the access, shall be submitted to and approved in writing by the Local Planning Authority. The provisions of the scheme thereby approved shall be complied with in full prior to the development being brought into use.

Reason: In the interests of the avoidance of congestion and of highway safety.