| Conditions or Reasons: | 1)
The development hereby permitted shall begin not later than three years from the date of this permission.
Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
2)
All external works hereby permitted shall be carried out in materials to match as closely as possible in colour, type and texture, those on plan numbers CBC-001 and CBC-002 and shall be retained thereafter.
Reason: To safeguard the appearance of the completed development by ensuring that the development hereby permitted is finished externally with materials to match the existing building in the interests of the visual amenities of the locality. (Section 12, NPPF) |
3)
The planting and landscaping scheme shown on approved Drawing No. PL05B dated April 2021 shall be implemented by the end of the full planting season immediately following the completion and/or first use of any separate part of the development (a full planting season shall mean the period from October to March). The trees, shrubs and grass shall subsequently be maintained for a period of five years from the date of planting and any which die or are destroyed during this period shall be replaced during the next planting season with others of a similar size and species.
Reason: To ensure an acceptable standard of landscaping. (Sections 12 & 15, NPPF) |
4)
A scheme shall be submitted for approval in writing by the Local Planning Authority indicating the positions, design, materials and type of boundary treatment to be erected. The boundary treatment shall be completed in accordance with the approved scheme [before the use hereby permitted is commenced / before the building(s) is/are occupied] and be thereafter retained.
Reason: To safeguard the appearance of the completed development and the visual amenities of the locality. (Section 12, NPPF) |
5)
The turning space for service vehicles illustrated on the approved Plan No PL05B shall be constructed before the development is first brought into use and retained as such in perpetuity.
Reason To enable vehicles to draw off, park and turn outside the highway limits thereby avoiding the reversing of vehicles on to the highway. |
6)
Before the development is first occupied or brought into use, the parking scheme shown on plan no PL05B shall be completed and thereafter retained for this purpose.
Reason To ensure the provision of car parking clear of the highway. |
7)
The development hereby permitted shall be undertaken in full accordance with the Councils adopted Construction Code of Practice for Developers and Contractors https://www.centralbedfordshire.gov.uk/info/44/planning/674/codes_of_practice_for_planning.
Reason: In order to minimise the impact of construction work on the amenities of nearby residential properties (Section 12, NPPF) |
8)
The development hereby permitted shall be undertaken in full accordance with the Councils adopted Environmental Code of Practice https://www.centralbedfordshire.gov.uk/info/44/planning/674/codes_of_practice_for_planning/3
Reason: In order to minimise the impact of development on existing trees, landscape features and biodiversity (Section 15, NPPF) |
9)
Prior to occupation, the electric vehcile charging points as outlined on Plan Number PL05B shall be constructed and retained thereafter.
Reason: To ensure the development protects and exploits opportunities for the use of sustainable transport modes for the movement of people in accordance with paragraph 105 e) of the National Planning Policy Framework 2019. |
10)
Notwithstanding the provisions of Part 1 Class E of Schedule 2 to the Town and Country (General Permitted Development) Order 2015 (or any order revoking and re-enacting that Order with or without modification), no buildings or other structures shall be erected or constructed within the curtilage of the property without the grant of further specific planning permission from the Local Planning Authority.
Reason: To control the development in the interests of the visual amenity of the area. (Section 12, NPPF) |
11)
The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers 01, 02, 03, 04, SM-B, PL01B, PL02B, PL03B, PL04B, PL05B, BP-B, CBC-001 and CBC-002