| Conditions or Reasons: | 1)
The development hereby permitted shall begin not later than three years from the date of this permission.
Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
2)
No external materials shall be applied to the building hereby approved until details of the materials have been submitted to and approved in writing by the Local Planning Authority. The development shall thereafter be carried out in accordance with the approved details. Reason: To control the appearance of the building in the interests of the visual amenities of the locality. (Section 12, NPPF) |
3)
No works above ground level shall take place until a landscaping scheme to include all hard and soft landscaping and a scheme for landscape maintenance for a period of five years following the implementation of the landscaping scheme have been submitted to and approved in writing by the Local Planning Authority. The approved scheme shall be implemented by the end of the full planting season immediately following the completion and/or first use of any separate part of the development (a full planting season means the period from October to March). The trees, shrubs and grass shall subsequently be maintained in accordance with the approved landscape maintenance scheme and any which die or are destroyed during this period shall be replaced during the next planting season.
Reason: To ensure an acceptable standard of landscaping. (Sections 12 & 15, NPPF) |
4)
No development shall take place until a scheme for protecting the proposed dwelling from external noise sources has been submitted to and approved in writing by the local plannin gauthority. The scheme shall follow the recommendations identified in the Syntegra Noise Impact Assessment report (Ref: 21-7886) dated March 2021. The dwelling shall not be occupied until such a scheme has been implemented in accordance with the approved details, and it shall be retained in accordance with those details thereafter.
Reason: To protect the amenity of future occupiers of the dwelling hereby approved. |
5)
The development hereby permitted shall not begin until a scheme to deal with contamination of land/ground gas/controlled waters has been submitted to and approved in writing by the local planning authority. The scheme shall include all of the following measures, unless the local planning authority dispenses with any such requirement specifically in writing:
1. A Phase I site investigation report carried out by a competent person to include a desk study, site walkover, the production of a site conceptual model and a human health and environmental risk assessment, undertaken in accordance with BS 10175: 2011 Investigation of Potentially Contaminated Sites Code of Practice. 2. A Phase II intrusive investigation report detailing all investigative works and sampling on site, together with the results of the analysis, undertaken in accordance with BS 10175:2011 Investigation of Potentially Contaminated Sites Code of Practice. The report shall include a detailed quantitative human health and environmental risk assessment. 3. A remediation scheme detailing how the remediation will be undertaken, what methods will be used and what is to be achieved. A clear end point of the remediation shall be stated, and how this will be validated. Any ongoing monitoring shall also be determined. 4. If during the works contamination is encountered which has not previously been identified, then the additional contamination shall be fully assessed in an appropriate remediation scheme which shall be submitted to and approved in writing by the local planning authority. 5. A validation report detailing the proposed remediation works and quality assurance certificates to show that the works have been carried out in full accordance with the approved methodology shall be submitted prior to first occupation of the development. Details of any post-remedial sampling and analysis to demonstrate that the site has achieved the required clean-up criteria shall be included, together with the necessary documentation detailing what waste materials have been removed from the site.
Reason: To minimise and prevent pollution of the land and the water environment and in accordance with national planning policy guidance set out in section 11 of the National Planning Policy Framework, and in order to protect human health and the environment |
6)
No development shall take place until a scheme has been submitted to and approved in writing by the Local Planning Authority for the provision of fire hydrants at the development. Prior to the first occupation of the dwelling(s) the fire hydrant(s) serving that development shall be installed as approved. Thereafter the fire hydrant(s) shall be retained as approved in perpetuity.
Reason: In the interests of fire safety and providing safe and accessible developments. (Section 7, NPPF) |
7)
The development hereby permitted shall be undertaken in full accordance with the Councils adopted Environmental Code of Practice https://www.centralbedfordshire.gov.uk/info/44/planning/674/codes_of_practice_for_planning/3
Reason: In order to minimise the impact of development on existing trees, landscape features and biodiversity (Section 15, NPPF) |
8)
The development hereby permitted shall be undertaken in full accordance with the Councils adopted Construction Code of Practice for Developers and Contractors https://www.centralbedfordshire.gov.uk/info/44/planning/674/codes_of_practice_for_planning.
Reason: In order to minimise the impact of construction work on the amenities of nearby residential properties (Section 12, NPPF) |
9)
The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers SE3315/4, SE3315/7, SE3315/6.
Reason: To identify the approved plan/s and to avoid doubt. |
|
|---|