<< Back to case
Conditions or Reasons for Planning Application - CB/21/02773/FULL
Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) All external works hereby permitted shall be carried out in materials to match as closely as possible in colour, type and texture, those of the existing buildings.

Reason: To safeguard the appearance of the completed development by ensuring that the development hereby permitted is finished externally with materials to match the existing building in the interests of the visual amenities of the locality.
(Section 12, NPPF)
3) Prior to the change of use hereby approved, a landscaping scheme to include all hard and soft landscaping including boundary treatments and a scheme for landscape maintenance for a period of five years following the implementation of the landscaping scheme have been submitted to and approved in writing by the Local Planning Authority. The approved scheme shall be implemented by the end of the full planting season immediately following the completion and/or first use of any separate part of the development (a full planting season means the period from October to March). The trees, shrubs and grass shall subsequently be maintained in accordance with the approved landscape maintenance scheme and any which die or are destroyed during this period shall be replaced during the next planting season.

Reason: To ensure an acceptable standard of landscaping and to protect visual amenities of the open countryside.
(Sections 12 & 15, NPPF)
4) The development hereby permitted shall be undertaken in full accordance with the Councils adopted Construction Code of Practice for Developers and Contractors https://www.centralbedfordshire.gov.uk/info/44/planning/674/codes_of_practice_for_planning.

Reason: In order to minimise the impact of construction work on the amenities of nearby residential properties (Section 12, NPPF)
5) The development hereby permitted shall not be occupied until a scheme for the parking of cycles on the site has been submitted to and approved in writing by the Local Planning Authority. The scheme shall be fully implemented before the development is first occupied and thereafter retained for this purpose.

Reason: To ensure the provision of cycle parking to meet the needs of occupiers of the proposed development in the interests of encouraging the use of sustainable modes of transport.
(Section 94, NPPF)
6) Notwithstanding the provisions of Part 1 Class E of Schedule 2 to the Town and Country (General Permitted Development) Order 2015 (or any order revoking and re-enacting that Order with or without modification), no buildings or other structures shall be erected or constructed within the curtilage of the properties without the grant of further specific planning permission from the Local Planning Authority.

Reason: To control the development in the interests of the visual amenity of the area and the openness of the South Bedfordshire Green Belt.
(Section 12 and 13, NPPF)
7) Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any order revoking and re-enacting that Order with or without modification), no fences, gates, walls or other means of enclosure shall be erected within the curtilage of the property without the grant of further specific planning permission from the Local Planning Authority.

Reason: To control the development in the interests of the rural amenity of the area.
(Section 12, NPPF)
8) Notwithstanding the provisions of Part 1, Class A of Schedule 2 to the Town and Country Planning (General Permitted Development) Order 2015 (or any order revoking and re-enacting that Order with or without modification), no extensions to the buildings hereby permitted shall be carried out without the grant of further specific planning permission from the Local Planning Authority.

Reason: To control the external appearance of the building/s in the interests of the amenities of the area and the South Bedfordshire Green Belt.
(Section 12 and 13, NPPF)
9) Prior to the first occupation of the residential units hereby approved, a scheme for the charging of electric and ultra-low emission vehicles shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall accord with Policy T5 of CBLP. The development shall be completed prior to occupation in accordance with these approved details.

Reason: To assist with the transition to low-emission vehicles in line with Policy T5 of the CBLP and paragraph 110 of the National Planning
10) Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any order revoking and re-enacting that Order with or without modification), the parking area shown on the approved plans shall be kept permanently available for the parking of motor vehicles.

Reason: To ensure that off-street parking is retained in the interests of highway safety.
(Policy T3 of the CBC Local Plan and NPPF)
11) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers RB/RG/0203, RB-RG-015, GBA 1013-01, RB-RG-002, RB-RG-002, RB-RG-004, RB-RG-005, Location Plan, Ground Floor Layout Pre-existing and First Floor Layout Pre-existing

Reason: To identify the approved plan/s and to avoid doubt.