Conditions or Reasons for Planning Application - CB/21/03124/NMA
Conditions or Reasons:
1) No external operations or activities between the hours of 23:00 to 07:00 shall take place at Unit 5 (as shown on the submitted Unit 5 Identification Plan Rev A), unless an operational management plan for night time operations has been approved by the Local Planning Authority. The operational management plan will need to include details of the type of operations proposed, the noise generated from such operations, how noise will be controlled during the night time period and demonstrate that the noise levels are acceptable. Operations will then only be allowed in strict accordance with the agreed management plan.

Reason: To protect the amenity of neighbouring residents.
(Section 12, NPPF July 2021, and Policy HQ1, CBLP July 2021)
2) Prior to the development hereby permitted first being brought into use, the active and passive locations for electric vehicle charging points shall be installed as shown on the Site Layout Plan (31112-PL-201 Rev L), and shall thereafter be retained.

Reason: To promote sustainable modes of transport.
(Section 9, NPPF July 2021, and Policy T5, CBLP July 2021)
3) The retention of existing landscaping and trees and the provision of proposed landscaping and trees shall be undertaken in accordance with approved plans 775.10.05 Rev C, 775.19.05 Rev B and 775.29.05 Rev A. This is with the exception of the proposed area to the south of the site indicated as 'wildflower and grass mix' which shall instead by used for extended tree planting, and where Oak and Beech are indicated in the central section of the southern boundary planting these shall be replaced with Sycamore and Field Maple. The proposed landscaping shall be implemented by the end of the full planting season immediately following the completion and/or first occupation of any separate part of the development (a full planting season means the period from October to March). The landscaping and trees shall subsequently be maintained and retained and any which die or are destroyed during this period shall be replaced during the next planting season.

Reason: To ensure an acceptable standard of landscaping.
(Sections 12 & 15, NPPF July 2021)
4) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers 31112-PL-200, 31112-PL-201 Rev L, 775 .TS.01 Rev A, 31112-PL-202 Rev A, 31112-PL-203 Rev A, 31112-PL-204 Rev C, 31112-PL-205 Rev C, 31112-PL-206 Rev B, 31112-PL-207 Rev B, 31112-PL-212 Rev D, 31112-PL-213 Rev D, 31112-PL-215 Rev D, 31112-PL-216 Rev A, 18-081 / 300 Rev P3, 18-081 / 301 Rev P3, 18-081 / 411 Rev P1, 775.10.05 Rev C, 775.19.05 Rev B, 775.29.05 Rev A, 31112-PL-218 Rev A, 31112 Acoustic Barrier Distance Sketch, 31112 Unit 5 Identification Plan Rev A, and 31112-PL-217 Rev B.

Reason: To identify the approved plans and to avoid doubt.