Conditions or Reasons:
12) Part 2 Final Condition 12
The development shall not begin until a scheme for the investigation and assessment to identify the extent and nature of contamination has been provided and agreed in writing by the Local Planning Authority. The scheme shall conform to Environmental Services 'Pre application guidance note on the assessment and remediation of land that may be affected by contamination for Environmental Consultants and Developers' and in doing so shall comprise of the following:
A phase 1 report (desk study), including a historical survey and conceptual model of the site.
A phase 2 report (Exploratory investigation), documenting the ground conditions of the site, incorporating chemical, gas and water analysis as identified as being appropriate by the phase 1 report
A Phase 3 report (Remediation Plan), detailing the remediation works to prevent any land from the site being designated as contaminated land following development
A phase 4 report (Validation), demonstrating proof and success of remedial works.
Reason: To ensure that any potential land contamination is identified and appropriate remedial measures taken to produce a site that is free from harm to humans and suitable for its proposed end use.