Conditions or Reasons for Planning Application - CB/21/04916/FULL
Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) No development approved by this permission shall take place until the following has been submitted to and approved in writing by the Local Planning Authority:

A Phase 1 Desk Study report prepared by a suitably qualified person adhering to The Environment Agency Land Contamination Risk Management (LCRM) documenting the ground and material conditions of the site with regard to potential contamination.

Reason: To protect human health and the environment in accordance with Policy HQ1 of the Central Bedfordshire Local Plan (2021).
3) No occupation of any permitted building shall take place until the following has been submitted to and approved in writing by the Local Planning Authority:

Where shown to be necessary by the Phase 1 Desk Study, a Phase 2 Site Investigation adhering to the Environment Agency Land Contamination Risk Management (LCRM), incorporating all appropriate sampling, prepared by a suitably qualified person.

Where shown to be necessary by the Phase 2 Site Investigation a detailed Phase 3 Remediation Scheme (RS) prepared by a suitably qualified person, with measures to betaken to mitigate any risks to human health, groundwater and the wider environment, along with a Phase 4 validation report prepared by a suitably qualified person to confirm the effectiveness of the RS. Any such remediation/validation should include responses to any unexpected contamination discovered during works.

Reason: To protect human health and the environment in accordance with Policy HQ1 of the Central Bedfordshire Local Plan (2021).
4) Development shall not begin until details of the junction of the proposed vehicular access with the highway have been approved by the Local Planning Authority and no building shall be occupied until the junction has been constructed in accordance with the approved details.

Reason In order to minimise danger, obstruction and inconvenience to users of the highway and the premises.
5) The proposed vehicular access shall be surfaced in bituminous or other similar durable material (not loose aggregate) as may be approved in writing by the Local Planning Authority for a distance of 5m into the site, measured from the highway boundary, before the premises are occupied. Arrangements shall be made for surface water drainage from the site to be intercepted and disposed of separately so that it does not discharge into the highway.

Reason To avoid the carriage of mud or other extraneous material or surface water from the site into the highway so as to safeguard the interest of highway safety.
6) Prior to occupation, a scheme for the secure and covered parking of cycles on the site (including the internal dimensions of the cycle parking area, stands/brackets to be used and access thereto), calculated at one cycle parking space per bedroom and 2 short stay spaces per unit, shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall be fully implemented before the development is first occupied or brought into use and thereafter retained for this purpose.

Reason To ensure the provision of adequate cycle parking to meet the needs of occupiers of the proposed development in the interests of encouraging the use of sustainable modes of transport.
7) Prior to the construction of vehicular parking areas associated with the approved development, a scheme for the charging of electric and ultra-low emission vehicles for the approved dwellings shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall accord with Policy T5 of the Central Bedfordshire Local Plan and shall include the following:
Details of active charging posts or passive provision such as cabling and electricity supply
Timescales / triggers for implementation of the scheme.

The development shall be completed in accordance with these approved details including the agreed timescales / triggers.
Reason: To assist with the transition to low-emission vehicles in line with Policy T5 of the Central Bedfordshire Local Plan (2021) and paragraph 112 of the National Planning Policy Framework
8) Notwithstanding the details submitted with the application, no works above slab level shall take place until details of the materials to be used for the external walls and roofs of the development hereby approved has been submitted to and approved in writing by the Local Planning Authority. The development shall thereafter be carried out in accordance with the approved details.

All window frames and doors installed in the approved building shall be coloured Anthracite or similar, unless otherwise agreed in writing by the Local Planning Authority.

Reason: To control the appearance of the building in the interests of the visual amenities of the locality, in accordance with Policy HQ1 of the Central Bedfordshire Local Plan and the NPPF.
9) The development hereby permitted shall be undertaken in full accordance with the Councils adopted Construction Code of Practice for Developers and Contractors https://www.centralbedfordshire.gov.uk/info/44/planning/674/codes_of_practice_for_planning.

Reason: In order to minimise the impact of construction work on the amenities of nearby residential properties (Section 12, NPPF)
10) The development hereby permitted shall be undertaken in full accordance with the Councils adopted Environmental Code of Practice https://www.centralbedfordshire.gov.uk/info/44/planning/674/codes_of_practice_for_planning/3

Reason: In order to minimise the impact of development on existing trees, landscape features and biodiversity (Section 15, NPPF)
11) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers GD/004, GD/001A, GD/002A, GD/003A.

Reason: To identify the approved plan/s and to avoid doubt.