Conditions or Reasons for Planning Application - CB/22/00907/DOC
Conditions or Reasons:
12) Prior to commencement of above ground works (excluding demolition) details of improvements to the junction of the vehicular access with the highway shall be approved by the Local Planning Authority and no building shall be occupied until the junction has been constructed in accordance with the approved details.

Reason: In order to minimise danger, obstruction and inconvenience to users of the highway and the premises.
17) Before the new access is first brought into use, any existing access within the frontage of the land to be developed, not incorporated in the access hereby approved shall be closed in a manner to the Local Planning Authority's written approval and constructed in accordance with the approved details.

Reason
In the interest of road safety and to reduce the number of points at which traffic will enter and leave the public highway.
21) No development approved by this permission shall take place until a Phase 2 investigation report, as recommended by the previously submitted STM Environmental Ltd report dated November 2019 (Ref: PH1-2019-000098), has been submitted to and approved in writing by the Local Planning Authority. Where found to be necessary by the phase 2 report a remediation strategy to deal with the risks associated with contamination of the site shall also be submitted to and approved in writing by the Local Planning Authority. The remediation strategy shall include an options appraisal giving full details of the remediation measures required and how they are to be undertaken. The strategy shall include a plan providing details of how the remediation works shall be judged to be complete and arrangements for contingency action.

Reason: To protect human health and to ensure that no future investigation is required under Part 2A of the Environmental Protection Act 1990.