Conditions or Reasons for Planning Application - CB/22/01198/DOC
Conditions or Reasons:
2) Prior to the construction phase of development, notwithstanding the details submitted with the application, details of the materials to be used for the external walls and roofs of the development hereby approved will have been submitted to and approved in writing by the Local Planning Authority. The development shall thereafter be carried out in accordance with the approved details.

Reason: To control the appearance of the building in the interests of the visual amenities of the locality.
(Section 12, NPPF)
3) A scheme shall be submitted for approval in writing by the Local Planning Authority indicating the positions, design, materials and type of boundary treatment to be erected. The boundary treatment shall be completed in accordance with the approved scheme before the buildings are occupied and shall be thereafter retained.

Reason: To safeguard the appearance of the completed development and the visual amenities of the locality.
(Section 12, NPPF)
8) No development shall take place (including ground works or site clearance) until a method statement for the creation of new wildlife features such as the erection of bird/bat boxes in buildings/structures and shrub and wildflower planting/establishment has been submitted to and approved in writing by the local planning authority. The content of the method statement shall include the:

a) purpose and objectives for the proposed works;
b) detailed design(s) and/or working method(s) necessary to achieve stated objectives (including, where relevant, type and source of materials to be used);
c) extent and location of proposed works shown on appropriate scale maps and plans;
d) timetable for implementation, demonstrating that works are aligned with the proposed phasing of construction;
e) persons responsible for implementing the works;

The works shall be carried out strictly in accordance with the approved details and shall be retained in that manner thereafter.

Reason: To ensure development is ecologically sensitive and secures biodiversity enhancements in accordance with the National Planning Policy Framework.
9) No development shall take place until a written scheme of archaeological investigation, that adopts a staged approach and includes the provision for post excavation analysis and publication, has been submitted to and approved in writing by the Local Planning Authority. The development hereby approved shall only be implemented in full accordance with the approved archaeological scheme."

Reason: This condition is pre-commencement as a failure to secure appropriate archaeological investigation in advance of development would be contrary to paragraph 199 of the National Planning Policy Framework (NPPF) that requires developers to record and advance of understanding of the significance of any heritage assets to be lost (wholly or in part) as a consequence of the development.
11) Development shall not begin until details of the improvements to the junction between the access road and the highway have been approved by the Local Planning Authority and no building shall be occupied until that junction has been constructed in accordance with the approved details.

Reason:
In order to minimise danger, obstruction and inconvenience to users of the highway and of the proposed estate