Conditions or Reasons:
3) Part A: No development shall take place until an archaeological written scheme of investigation (WSI), has been submitted to and approved in writing by the Local Planning Authority.

The WSI shall include the following components:

method statements for the investigation of all archaeological remains present at the site
method statements for the preservation in situ of any archaeological remains that cannot be fully investigated (if appropriate)
an outline strategy for post-excavation assessment, analysis and publication, including details of the timetable for each stage of the post-excavation works

Part B: The said development shall only be implemented in full accordance with the approved WSI and this condition shall only be fully discharged when:

it has been confirmed in writing by the Local Planning Authority that all elements of the archaeological fieldwork have been completed
a Post Excavation Assessment report and an Updated Project Design or a final archaeological report has been submitted to and approved in writing by the Local Planning Authority. This shall be done within twelve months of the completion of the archaeological fieldwork unless otherwise agreed in advance in writing by the Local Planning Authority
the post-excavation analysis as specified in the approved Updated Project Design (if a UPD is prepared) has been completed
the preparation of the site archives (both physical and digital) for deposition at stores approved by the Local Planning Authority has been undertaken and confirmed in writing by the Local Planning Authority. For the digital archive this will include confirmation of the intention to deposit with a CoreTrustSeal certified repository dedicated to storing archaeological archives.
the preparation of an archive report and the submission of a publication report have been completed and confirmed in writing by the Local Planning Authority

Unless otherwise agreed in advance in writing by the Local Planning Authority, items 3 and 4 of Part B of this condition shall be completed within 2 years of the archaeological fieldwork date of completion. Item 5 shall be completed within 3 years of the archaeological fieldwork date of completion.

This condition is pre-commencement as a failure to secure archaeological investigation in advance of development, to secure the long term future of the archive and to make the record of that work publicly available would be contrary to policy HE1 of the Central Bedfordshire Local Plan 2015-2035 (adopted July 2021) and paragraph 205 of the National Planning Policy Framework that requires developers to record and advance of understanding of the significance of any heritage assets affected by development before they are lost (wholly or in part).