Conditions or Reasons for Planning Application - CB/22/01819/DOC
Conditions or Reasons:
2) Prior to commencement of works beyond those already detailed in the Chapel Farm Commencement of Development Works Plan (ref. no. CBC -02), storm water details (design and construction) shall be submitted to and approved in writing by the Local Planning Authority. Storage must be provided for all storm events up to and including the 1 in 100 year event + 40% allowance for climate change.

Reason: To ensure an acceptable scheme. The proposed means of surface water discharge is direct to a watercourse under the IDB's control and the Board will not accept discharge rates greater and the QBAR rate for the site impermeable area
3) Prior to commencement of works beyond those already detailed in the Chapel Farm Commencement of Development Works Plan (ref. no. CBC -02), a scheme setting out details of turning areas suitable for a heavy goods vehicle shall be submitted to and approved by the Local Planning Authority and no operational use shall take place until those turning areas have been constructed in accordance with the approved details.

Reason: To enable vehicles to draw off, park and turn outside the highway limits thereby avoiding the reversing of vehicles on to the highway.
5) The proposed vehicular access shall be constructed and surfaced in accordance with details to be approved in writing by the Local Planning Authority for a distance of 25m into the site, measured from the highway boundary. Arrangement shall be made for surface water drainage from the site to be intercepted and disposed of separately so that it does not discharge into the highway.

Reason: To avoid the carriage of mud or other extraneous material or surface water from the site into the highway so as to safeguard the interest of the highway.(Section 9, NPPF)