Conditions or Reasons for Planning Application - CB/22/02671/DOC
Conditions or Reasons:
6) Prior to the commencement of the development, hereby approved, a Conservation Management Plan (CMP), covering archaeological, ecological and historic landscape matter, in addition to details of the body vested with ownership and with responsibility for management of the site, shall be submitted to the Local Planning Authority for approval in writing. The CMP shall be in relation to the area of woodland containing the County Wildlife Site and Scheduled Ancient Monument, as shown on drawing number 15139 (D) 202 Rev.D. No dwellings shall be occupied until a programme and timetable for the implementation of the Conservation Management Plan has been submitted to and agreed in writing with the Local Planning Authority.

Reason: To ensure that the development would be acceptable in accordance with Policy BE8 of the adopted Local Plan, Policy HQ1 of the emerging Local Plan and Section 16 of the NPPF. This is a pre-commencement condition as it is important to ensure that the management of the designated and other heritage assets are secured before development begins.
28) No development shall take place (including ground works or site clearance) until an Ecological Enhancement Strategy (EES) for the creation of new wildlife features such as hibernacula, the erection of bird/bat and bee boxes in buildings/structures and tree, hedgerow, shrub and wildflower planting/establishment has been submitted to and approved in writing by the local planning authority. The content shall be informed by an up to date Ecological Appraisal of the site and include the:

a) purpose and objectives for the proposed works;
b) detailed design(s) and/or working method(s) necessary to achieve stated
objectives (including, where relevant, type and source of materials to be used);
c) extent and location of proposed works shown on appropriate scale maps and plans;
d) timetable for implementation, demonstrating that works are aligned with the proposed phasing of construction;
e) persons responsible for implementing the works;
f) details of initial aftercare and long-term maintenance.

The works shall be carried out strictly in accordance with the approved details and shall be retained in that manner thereafter.

Reason: In the interests of providing a net benefit in terms of ecology, in accordance with the NPPF.