Conditions or Reasons for Planning Application - CB/22/02878/DOC
Conditions or Reasons:
2) Development shall not begin until details of the junction of the proposed vehicular access with the highway have been approved by the Local Planning Authority and no building shall be occupied until the junction has been constructed in accordance with the approved details.

Reason: In order to minimise danger, obstruction and inconvenience to users of the highway and the premises. (Section 9, NPPF)
4) No development shall commence until a detailed surface water drainage scheme, to manage surface water runoff from the development for up to and including the 1 in 100 year event (+40%CC), and a maintenance and management plan for the scheme has been submitted to and approved in writing by the Local Planning Authority. The discharge rate from the development will be limited to the equivalent 1 in 1 year rate, or an appropriate rate as agreed by the LLFA. The final detailed design shall be based on DEFRAs Non-statutory technical standards for sustainable drainage systems (March 2018) and shall be implemented and maintained as approved. Maintenance will ensure the system functions as designed for the lifetime of the development. Any variation to the connections and controls indicated on the approved drawing which may be necessary at the time of construction would require the resubmission of those details to the Local Planning Authority for approval.

Reason: To ensure the approved system will function to a satisfactory minimum standard of operation and maintenance and prevent the increased risk of flooding both on and off site, in accordance with paragraph 163 and 165 of the NPPF and its supporting technical guidance.
5) No building/dwelling shall be occupied until the developer has formally submitted in writing to the Local Planning Authority a finalised 'Maintenance and Management Plan' for the entire surface water drainage system, inclusive of any adoption arrangements and/or private ownership or responsibilities, and that the approved surface water drainage scheme has been correctly and fully installed as per the final approved details.

Reason: To ensure that the implementation and long term operation of a sustainable drainage system (SuDS) is in line with what has been approved, in accordance with Written Statement HCWS161, 18th December 2014.
6) No development shall commence above ground level until a scheme (based on current government policy/guidance at the time of submission) for the provision of electric charging points has been submitted to and approved in writing by the local planning authority. The charging points shall be provided as approved prior to the occupation of the buildings they serve.

Reason: To ensure the development protects and exploits opportunities for the use of sustainable transport modes for the movement of people in accordance with paragraph 112 e) of the National Planning Policy Framework 2021.
7) No development shall take place, notwithstanding the details submitted with the application, until details of the materials to be used for the external walls and roofs of the development hereby approved have been submitted to and approved in writing by the Local Planning Authority. The development shall thereafter be carried out in accordance with the approved details.

Reason: To control the appearance of the building in the interests of the visual amenities of the locality. (Section 12, NPPF)
8) No development shall commence above ground level until a landscaping scheme to include all hard and soft landscaping and a scheme for landscape maintenance for a period of five years following the implementation of the landscaping scheme have been submitted to and approved in writing by the Local Planning Authority. The approved scheme shall be implemented by the end of the full planting season immediately following the completion and/or first use of any separate part of the development (a full planting season means the period from October to March). The trees, shrubs and grass shall subsequently be maintained in accordance with the approved landscape maintenance scheme and any which die or are destroyed during this period shall be replaced during the next planting season.

Reason: To ensure an acceptable standard of landscaping.
(Sections 12 & 15, NPPF)