Conditions or Reasons:
3) No demolition or development shall take place until a written scheme of archaeological investigation; that includes provision for post excavation analysis and publication, has been submitted to and approved in writing by the Local Planning Authority. The development hereby approved shall only be implemented in full accordance with the approved archaeological scheme.
Reason: This condition is pre-commencement as a failure to secure appropriate archaeological investigation in advance of development would be contrary to paragraph 199 of the National Planning Policy Framework (NPPF) that requires developers to record and advance of understanding of the significance of any heritage assets to be lost (wholly or in part) as a consequence of the development.
11) The development hereby permitted shall not be commenced until a detailed surface water drainage design has been submitted to, and approved in writing by, the local planning authority. The design shall subsequently be fully implemented and maintained, in accordance with the timing / phasing arrangements embodied within the scheme, or within any other period as may subsequently be agreed, in writing, by the local planning authority.

Reason: To ensure the approved system will function to a satisfactory minimum standard of operation and prevent the increased risk of flooding both on and off site for the lifetime of the development in accordance with para 163 NPPF; and to ensure that the implementation and long term operation of a sustainable drainage system (SuDS) is in line with what has been approved, in accordance with Written statement - HCWS161
12) No works shall commence unless the local planning authority has been provided with either:

a) a licence issued by Natural England pursuant to Regulation 53 of The Conservation of Habitats and Species Regulations 2010 authorizing the specified activity/development to go ahead; or
b) a statement in writing from the relevant licensing body to the effect that it does not consider that the specified activity/development will require a licence.

Reason: To ensure the safety of protected species, this needs to be pre-commencement so no works commence disturbing existing habitat.