5) No development shall take place until a scheme has been submitted to and approved in writing by the Local Planning Authority for the provision of fire hydrants at the development. Prior to the first occupation of the dwelling(s) the fire hydrant(s) serving that development shall be installed as approved. Thereafter the fire hydrant(s) shall be retained as approved in perpetuity.

Reason: In the interests of fire safety and providing safe and accessible developments. (Section 7, NPPF)
10) Before development begins, a scheme for the secure and covered parking of cycles on the site (including the internal dimensions of the cycle parking area, stands/brackets to be used and access thereto), calculated at one cycle parking space per bedroom and 2 short stay spaces per unit, shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall be fully implemented before any dwelling is first occupied or brought into use and thereafter retained for this purpose.

Reason: To ensure the provision of adequate cycle parking to meet the needs of occupiers of the proposed development in the interests of encouraging the use of sustainable modes of transport
11) Details of a refuse collection point located at the site frontage and outside of the public highway and any visibility splays shall be submitted to and approved by the Local Planning Authority prior to the occupation of any dwelling. The scheme shall be fully implemented prior to occupation of any dwelling and shall be retained thereafter.

Reason: In the interest of amenity and in order to minimise danger, obstruction and inconvenience to users of the highway and the premises
12) No works are in any circumstances to commence unless the local planning authority has been provided with either:

a) a licence issued by Natural England authorizing the specified activity/development to go ahead; or

b) a statement in writing from the relevant licensing body to the effect that it does not consider that the specified activity/development will require a licence.

Reason: To ensure the development causes no harm to protected species in accordance with policy EE2 of the Central Bedfordshire Local Plan.
14) No development shall commence until a detailed site-specific Arboricultural Impact Assessment and Tree Protection Plan has been submitted to and approved in writing by the local planning authority. The proposed development shall be carried out in strict accordance with the details thereby approved.

Reason: To ensure the appropriate safeguarding, management and mitigation of existing trees and hedgerows on the site. (Sections 12 & 15, NPPF)
17) No development approved by this permission shall take place until the following has been submitted to and approved in writing by the Local Planning Authority:

A Phase 1 Desk Study report documenting the ground conditions of the site with regard to potential contamination This report shall adhere to BS10175:2011.
A Phase 2 Site Investigation (where shown as necessary the Phase 1 Desk Study )
A Phase 3 Remediation Scheme (where shown as necessary by the Phase 2 Site Investigation)

All such work shall be undertaken in accordance with BS:10175:2011 or other appropriate guidance issued by the regulatory authorities. The work shall be sufficient to ensure that measures will be taken to mitigate any risks to human health, groundwater and the wider environment.

Reason: To protect human health and the environment
20) Prior to the occupation of any dwelling hereby approved, a scheme for the charging of electric and ultra-low emission vehicles shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall accord with Policy T5 of CBLP and shall include the following:

Details of active charging posts or passive provision such as cabling and electricity supply for each parking space
Timescales / triggers for implementation of the scheme.

The development shall be completed in accordance with these approved details including the agreed timescales / triggers.

Reason: To assist with the transition to low-emission vehicles in line with Policy T5 of the CBLP and paragraph 110 of the National Planning
21) Prior to the commencement of development, details of the existing and final ground levels and slab levels for buildings has been submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in full accordance with the approved details.

Reason: Details are required prior to the commencement of development to ensure that an acceptable relationship results between the new development and adjacent buildings, private amenity spaces and public areas, in accordance with Policy HQ1 of the Central Bedfordshire Local Plan (2021) and the NPPF