6) 6) The use hereby permitted shall cease and all caravans, structures, equipment
and materials brought onto the land for the purposes of that use shall be
removed within 3 months of the date of failure to meet any of the requirements
set out in (i) to (iv) below:
(i) Within 3 months of the date of this decision, or such other period as the Local
Planning Authority may agree in writing, a scheme shall be submitted in writing
to the Local Planning Authority for its written approval. The scheme shall
include details of the following:
a) A site layout plan showing the position of four static caravans, car parking
spaces, up to four touring caravan storage bays, satisfactory turning area
for commercial vehicles and any CCTV poles and cameras to be retained
on the site;

b) a landscaping scheme for the site, clearly identifying details of all tree,
hedge and shrub planting including details of species, plant sizes and
Appeal Decisions APP/P0240/C/21/3276356 & 3276367
https://www.gov.uk/planning-inspectorate 14
proposed numbers as well as the material and height detail of any boundary
treatment;

c) a detailed surface water drainage scheme and maintenance and
management scheme, with evidence of a viable means of discharge off
site. The details to be provided must demonstrate the drainage scheme will
be effective in all storm events up to and including the 1 in 100-year event
(+40%CC). Where existing drainage is to be retained details to
demonstrate this is of suitable condition and capacity must be provided;

d) a scheme to provide foul waste water and disposal having regard to the
Environment Agency's hierarchy for discharge and Building Regulation H
List of Priority;

e) a scheme of acoustic mitigation measures for the four static caravans
which: meets or exceed the acoustic requirements of BS3632:2015
Residential Park Home; incorporates suitable uprated windows and
ventilation openings if/as necessary to achieve internal conditions
commensurate with the daytime and night-time internal noise levels
detailed in Table 4 of BS8233:2014; includes details of an acoustic barrier
optimized to reduce noise impact in external areas to comply with the
requirements of BS8233:2014; and assesses the impact of any acoustic
mitigation measures to all neighbouring residential properties,

f) a scheme for the storage of waste and recyclables,

g) a scheme to demonstrate biodiversity net gains having regard to an agreed
pre incursion baseline and using the Natural England Biodiversity Metric
3.1 (or any subsequently replacement),

h) a scheme for external lighting at the appeal site, and
i) a timetable for the implementation and retention of each element of the
scheme.
(ii) Within 9 months of the date of this decision, the scheme referred to above shall
have been approved by the Local Planning Authority or, if the Local Planning
Authority refuses to approve the scheme or fails to give a decision within the
prescribed period, an appeal shall have been made to, and accepted by, the
Secretary of State.
(iii) If an appeal is made in pursuance of (ii) above, that appeal shall have been
finally determined and the submitted scheme shall have been finally approved
by the Secretary of State.
(iv) The approved scheme shall have been carried out and completed in
accordance with the approved timetable and the approved scheme shall
thereafter apply.
(v) In the event of a legal challenge to this decision, or to a decision made pursuant
to the procedure set out in this condition, the operation of the time limits
specified in this condition will be suspended until that legal challenge has been
finally determined.