Conditions or Reasons for Planning Application - CB/23/03031/FULL
Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) All external works hereby permitted shall be carried out in materials to match as closely as possible in colour, type and texture, those specified within the submitted application form.

Reason: To safeguard the appearance of the completed development in the interests of the visual amenities of the locality.
(Section 12, NPPF)
3) The building hereby approved shall only be used for agricultural purposes and for no other purpose.

Reason: To prevent an inappropriate development in the Green Belt.
(Section 13, NPPF)
4) The development hereby permitted shall be undertaken in full accordance with the Councils adopted Construction Code of Practice for Developers and Contractors https://www.centralbedfordshire.gov.uk/info/44/planning/674/codes_of_practice_for_planning.

Reason: In order to minimise the impact of construction work on the amenities of nearby residential properties (Section 12, NPPF)
5) The development hereby permitted shall be undertaken in full accordance with the Councils adopted Environmental Code of Practice https://www.centralbedfordshire.gov.uk/info/44/planning/674/codes_of_practice_for_planning/3

Reason: In order to minimise the impact of development on existing trees, landscape features and biodiversity (Section 15, NPPF)
6) Prior to any above ground development, an Ecological Enhancement Strategy (EES) for the creation of new wildlife features such as hibernacula, the inclusion of integrated bird/bat and bee boxes in buildings/structures, hedgehog holes in fences and tree, hedgerow, shrub and wildflower planting/establishment shall be submitted to and approved in writing by the Local Planning Authority. The content shall include the:

a) purpose and objectives for the proposed works;
b) detailed design(s) and/or working method(s) necessary to achieve stated objectives (including, where relevant, type and source of materials to be used);
c) extent and location of proposed works shown on appropriate scale maps and plans;
d) timetable for implementation, demonstrating that works are aligned with the proposed phasing of construction;
e) persons responsible for implementing the works;
f) details of initial aftercare and long-term maintenance.

The works shall be carried out strictly in accordance with the approved details and shall be retained in that manner thereafter.

Reason: To ensure development is ecologically sensitive and secures biodiversity enhancements in accordance with the National Planning Policy Framework
(Section 15, NPPF)
7) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers 1970/1A, 1970/2 and 1970/3A.

Reason: To identify the approved plan/s and to avoid doubt.