Conditions or Reasons for Planning Application - CB/23/03263/FULL
Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers:

PL L100 Rev 02 Site Plan,
PL L101 Ground floor Rev 05
PL10 Block Plan (GL)
PL 102 Rev 01 - Foundry Lane First Floor Plan
PL103 Rev 01 - Foundry Land Second Floor Plan
PL104 Rev 01 - Foundry Land Third Floor Plan
PL105 Rev 01 - Foundry Land Roof Plan
PL106 South Elevation Rev 01
PL107 North Elevation Rev 01
PL108 East Elevation Rev 02
PL109 Proposed West Elevation Plan
PL11 Block Plan (RL)
PL12 Existing Plans Elevations

Reason: To identify the approved plans and to avoid doubt.
3) No above ground works shall take place until details of the materials to be used in the construction of the external surfaces of the development hereby permitted have been submitted to and approved in writing by the Local Planning Authority. The development shall thereafter be carried out in accordance with the approved details.

Reason: To control the appearance of the building in the interests of the visual amenities of the locality. (Section 12, NPPF)
4) No development above slab level shall take place until a landscaping scheme to include all hard and soft landscaping and a scheme for landscape maintenance for a period of five years following the implementation of the landscaping scheme have been submitted to and approved in writing by the Local Planning Authority. The approved scheme shall be implemented by the end of the full planting season immediately following the completion and/or first use of any separate part of the development (a full planting season means the period from October to March). The trees, shrubs and grass shall subsequently be maintained in accordance with the approved landscape maintenance scheme and any which die or are destroyed during this period shall be replaced during the next planting season.

Reason: To ensure an acceptable standard of landscaping. (Sections 12 and 15, NPPF)
5) No building shall be occupied until the junction of the proposed vehicular access with the highway has been constructed in accordance with the approved details.
Reason: In order to minimise danger, obstruction and inconvenience to users of the highway and the premises.
6) Visibility splays shall be provided at the junction of the access with the public highway before the development is brought into use. The minimum dimensions to provide the required splay lines shall be 2.4m measured along the centre line of the proposed access from its junction with the channel of the public highway and 25m measured from the centre line of the proposed access along the line of the channel of the public highway. The required vision splays shall for the perpetuity of the development remain free of any obstruction to visibility for 600mm above the adjacent carriageway level.
Reason: To provide adequate visibility between the existing highway and the proposed access(es), and to make the access(es) safe and convenient for the traffic which is likely to use it (them).
7) Before the development is brought into use, the proposed development shall be carried out and completed in all respects in accordance with the access siting and layout illustrated on the approved plan No.PL-L101 Rev 05 and defined by this permission and, notwithstanding the provision of the Town and Country Planning General Permitted Development Order 2015, (or any Order revoking or re-enacting that Order) there shall be no variation without the prior approval in writing of the Local Planning Authority.
Reason: To ensure that the development of the site is completed insofar as its various parts are interrelated and dependent one upon another and to provide adequate and appropriate access arrangements at all times.
8) The proposed vehicular access shall be surfaced in bituminous or other similar durable material (not loose aggregate) for a distance of 5m into the site, measured from the highway boundary, before the premises are occupied. Arrangements shall be made for surface water drainage from the site to be intercepted and disposed of separately so that it does not discharge into the highway.
Reason: To avoid the carriage of mud or other extraneous material or surface water from the site into the highway so as to safeguard the interest of highway safety.
9) No development shall take place, including any works of demolition, until a Construction Traffic Management Plan, associated with the development of the site, has been submitted and approved in writing by the Local Planning Authority which will include information on:
(a) The parking of vehicles
(b) Loading and unloading of plant and materials used in the development
(c) Storage of plant and materials used in the development
(d) The erection and maintenance of security hoarding / scaffolding affecting the highway if required.
(e) Wheel washing facilities
(f) Measures on site to control the deposition of dirt / mud on surrounding roads during the development.
(g) Footpath/footway/cycleway or road closures needed during the development period
(h) Traffic management needed during the development period.
(i) Times, routes and means of access and egress for construction traffic and delivery vehicles (including the import of materials and the removal of waste from the site) during the development of the site.

The approved Construction Management Plan associated with the development of the site shall be adhered to throughout the development process.

Reason: In the interests of safety, protecting the amenity of local land uses, neighbouring residents and highway safety.
10) Part A: No development shall take place until an archaeological Written Scheme of Investigation (WSI), has been submitted to and approved in writing by the Local Planning Authority. The WSI shall contain the following components: 
 
a method statement for the investigation of any archaeological remains that will be affected by the development 
an outline strategy for post-excavation assessment, analysis, archive preparation and publication, including details of the timetable for each stage of the post-excavation works 

The said development shall only be implemented in full accordance with the approved archaeological scheme. 
 
Part B: This condition shall only be fully discharged when: 
 
all elements of the archaeological fieldwork have been undertaken and the date of completion has been confirmed in writing by the Local Planning Authority 
the post-excavation assessment, analysis and final archaeological report has been submitted to and approved in writing by the Local Planning Authority. This shall be done within 8 months of the date of completion of the archaeological fieldwork unless otherwise agreed in advance in writing by the Local Planning Authority 
the preparation of the site archives (including the production of an archive report) for deposition at stores approved by the Local Planning Authority has been undertaken and confirmed in writing by the Local Planning Authority. For the digital archive this will include confirmation of the intention to deposit with a CoreTrustSeal certified repository dedicated to storing archaeological archives. 
the publication report text has been prepared for submission to a recognised archaeological journal, or an approved final archaeological report is submitted for inclusion in the Historic Environment Record, and this has been confirmed in writing by the Local Planning Authority  
 
Unless otherwise agreed in advance in writing by the Local Planning Authority, items 3, and 4 of Part B of this condition shall be completed within 18 months of the archaeological fieldwork date of completion.  
 
Reason: In line with policy HE1 of the Central Bedfordshire Local Plan 2015-2035 (adopted July 2021) and paragraph 205 of the National Planning Policy Framework (July 2021): to investigate and record any archaeological remains affected by the development, to safeguard the long-term future of the archive and to make the record of all the work publicly available. Part A of this condition is pre-commencement because development works can have an irreversible impact on archaeological remains and an approved programme of investigation must be in place before the development starts. 
 
This is advice is in line with Chapter 18 of the Central Bedfordshire Local Plan 2015-2035 (adopted 2021) and Chapter 16, NPPF (2021).
11) Prior to the occupation of any dwelling on the site, a scheme for the provision of waste receptacles for each dwelling shall be submitted to and agreed in writing by the Local Planning Authority. The receptacles shall be provided before occupation takes place.

Reason: In the interest of residential amenity and to reduce waste generation in accordance with the Councils's Minerals and Waste Local Plan 2014, Policy WSP5 and the adopted SPD "Managing Waste in New Developments" (2006).
12) The development hereby permitted shall be undertaken in full accordance with the Councils adopted Environmental Code of Practice https://www.centralbedfordshire.gov.uk/info/44/planning/674/codes_of_practice_for_planning/3

Reason: In order to minimise the impact of development on existing trees, landscape features and biodiversity (Section 15, NPPF)
13) The development hereby permitted shall be undertaken in full accordance with the Councils adopted Construction Code of Practice for Developers and Contractors https://www.centralbedfordshire.gov.uk/info/44/planning/674/codes_of_practice_for_planning.

Reason: In order to minimise the impact of construction work on the amenities of nearby residential properties (Section 12, NPPF)