Conditions or Reasons: | 5)
No equipment, machinery or materials shall be brought on to the site for the purposes of development until details of substantial protective fencing for the protection of any retained tree(s), has been submitted to and approved in writing by the Local Planning Authority. The approved fencing shall be maintained until all equipment, machinery and surplus materials have been removed from the site. Nothing shall be stored or placed in any area fenced in accordance with this condition and the ground levels within those areas shall not be altered, nor shall any excavation be made.
Reason: To protect the trees so enclosed in accordance with Section 8 of BS 5837 of 2012 or as may be subsequently amended. (Sections 12 & 15, NPPF) |
10)
Before the premises are occupied all on site vehicular areas shall be surfaced in a stable and durable materials in accordance with details to be approved in writing by the Local Planning Authority. Arrangements shall be made for surface water drainage from the vehicular areas to soak away within the site so that it does not discharge into the highway or into the main drainage system.
Reason: To avoid the carriage of mud or other extraneous material or surface water from the site so as to safeguard the interest of highway safety and reduce the risk of flooding and to minimise inconvenience to users of the premises and ensure satisfactory parking of vehicles outside highway limits. |
13)
Part A: No development shall take place until the previously submitted Minerva Archaeology Ltd Archaeological Written Scheme of Investigation (WSI), has been updated to reflect current planning application, application name, and current Archaeological Standards and Guidance, and has been re-submitted to and approved in writing by the Local Planning Authority. The WSI shall contain the following components:
1. a method statement for the investigation of any archaeological remains that will be affected by the development 2.an outline strategy for post-excavation assessment, analysis, archive preparation and publication, including details of the timetable for each stage of the post-excavation works
The said development shall only be implemented in full accordance with the approved archaeological scheme.
Part B: This condition shall only be fully discharged when:
1. all elements of the archaeological fieldwork have been undertaken and the date of completion has been confirmed in writing by the Local Planning Authority 2. the post-excavation assessment, analysis and final archaeological report has been submitted to and approved in writing by the Local Planning Authority. This shall be done within 8 months of the date of completion of the archaeological fieldwork unless otherwise agreed in advance in writing by the Local Planning Authority 3. the preparation of the site archives (including the production of an archive report) for deposition at stores approved by the Local Planning Authority has been undertaken and confirmed in writing by the Local Planning Authority. For the digital archive this will include confirmation of the intention to deposit with a Core Trust Seal certified repository dedicated to storing archaeological archives. 4. the publication report text has been prepared for submission to a recognised archaeological journal, or an approved final archaeological report is submitted for inclusion in the Historic Environment Record, and this has been confirmed in writing by the Local Planning Authority.
Unless otherwise agreed in advance in writing by the Local Planning Authority, items 3, and 4 of Part B of this condition shall be completed within 18 months of the archaeological fieldwork date of completion.
Reason: In line with policy HE1 of the Central Bedfordshire Local Plan 2015-2035 (adopted July 2021) and paragraph 205 of the National Planning Policy Framework (July 2021): to investigate and record any archaeological remains affected by the development, to safeguard the long-term future of the archive and to make the record of all the work publicly available. Part A of this condition is pre-commencement because development works can have an irreversible impact on archaeological remains and an approved programme of investigation must be in place before the development starts.This is advice is in line with Chapter 18 of the Central Bedfordshire Local Plan 2015-2035 (adopted 2021) and Chapter 16, NPPF (2021). |
14)
No above ground development shall take place until a scheme for protecting the proposed dwellings from noise arising from neighbouring commercial and transport sources has been submitted to and approved in writing by the local planning authority. The scheme shall follow the recommendations identified in the Joynes Nash Sound Exposure Assessment report (Ref: Version 1.2) dated September 2020. The dwelling shall not be occupied until such a scheme has been implemented in accordance with the approved details, and shown to be effective, and it shall be retained in accordance with those details thereafter.
Reason: To protect the amenity of future occupiers of the development. |
17)
Prior to the construction of vehicular parking areas associated with the approved dwelling, a scheme for the charging of electric and ultra-low emission vehicles shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall accord with Policy T5 of CBLP and shall include the following:
Details of active charging posts or passive provision such as cabling and electricity supply Timescales / triggers for implementation of the scheme.
The development shall be completed in accordance with these approved details including the agreed timescales / triggers.
Reason: To assist with the transition to low-emission vehicles in line with Policy T5 of the CBLP and paragraph 110 of the National Planning |
|
---|