<< Back to case
Conditions or Reasons for Planning Application - CB/24/00316/DOC
Conditions or Reasons:
4) External lighting

a). Before the changing barn hereby approved is brought into use details of external artificial lighting shall be submitted to and approved in writing by the Local Planning Authority. Lighting contours shall be submitted to demonstrate that the vertical illumination of neighbouring premises is in accordance with the recommendations of the Institution of Lighting Professionals in the 'Guidance Note 01/20: Guidance Notes for the Reduction of Obtrusive Light'. Details should also be submitted for approval of measures to minimise use of lighting and prevent glare and sky glow by correctly using, locating, aiming and shielding luminaires. Lighting colour shall be warm in appearance and not exceeding a temperature of 3000 kelvin (K). Approved details shall be implemented prior to occupation of the changing barn and thereafter be permanently retained.

b). Before the pavilion building hereby approved is brought into use details of external artificial lighting shall be submitted to and approved in writing by the Local Planning Authority. Lighting contours shall be submitted to demonstrate that the vertical illumination of neighbouring premises is in accordance with the recommendations of the Institution of Lighting Professionals in the 'Guidance Note 01/20: Guidance Notes for the Reduction of Obtrusive Light'. Details should also be submitted for approval of measures to minimise use of lighting and prevent glare and sky glow by correctly using, locating, aiming and shielding luminaires. Lighting colour shall be warm in appearance and not exceeding a temperature of 3000 kelvin (K). Approved details shall be implemented prior to occupation of the pavilion building and thereafter be permanently retained.

Reason: To minimise light pollution and protect the amenities of nearby residential properties. (NPPF Section 15)
7) Landscaping

a). No development above slab level of the changing barn hereby approved shall take place until a landscaping scheme to include all hard and soft landscaping and a scheme for landscape maintenance for a period of five years following the implementation of the landscaping scheme have been submitted to and approved in writing by the Local Planning Authority. The approved scheme shall be implemented by the end of the full planting season immediately following the completion and/or first use of any separate part of the development (a full planting season means the period from October to March). The trees, shrubs and grass shall subsequently be maintained in accordance with the approved landscape maintenance scheme and any which die or are destroyed during this period shall be replaced during the next planting season.

b). No development above slab level of the pavilion building hereby approved shall take place until a landscaping scheme to include all hard and soft landscaping and a scheme for landscape maintenance for a period of five years following the implementation of the landscaping scheme have been submitted to and approved in writing by the Local Planning Authority. The approved scheme shall be implemented by the end of the full planting season immediately following the completion and/or first use of any separate part of the development (a full planting season means the period from October to March). The trees, shrubs and grass shall subsequently be maintained in accordance with the approved landscape maintenance scheme and any which die or are destroyed during this period shall be replaced during the next planting season.

Reason: To ensure an acceptable standard of landscaping. (Sections 12 and 15, NPPF)