Conditions or Reasons for Planning Application - CB/24/01815/LB
Conditions or Reasons:
1) The works shall begin not later than three years from the date of this consent.

Reason: To comply with Section 18 of the Planning (Listed Buildings and Conservation Areas) Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) This consent relates only to the details shown on the submitted plans, numbers:
30465D_01_100 Rev. P1 Site location plan1:20,000
30465D_01_101 Rev. P1 Site location plan1:5000
30465D_01_102 Rev. P1 Site location Plan 1:500
30465D_01_103 Existing Plans
30465D_01_104 Existing Sections and Elevation 1/3
30465D_01_105 Existing Sections and Elevation 2/3
30465D_01_106 Existing Sections and Elevation 3/3
30465D_02_103 Block Plan
3046530465D_02_104 Rev. C - Proposed Faceted glass plans
30465D_02_105 Rev. A - Proposed Sections and Elevation 1/3
30465D_02_106 Rev. A Proposed Sections and Elevation 2/3
30465D_02_107 Rev. C Proposed Sections and Elevation 3/3
30465D_02_108 Rev. B Proposed Ring Beam and Gutter Details
30465D_02_109 Rev. A Proposed Visual
30465D_02_110 Rev. A Proposed Column Details




Reason: To identify the approved plan/s and to avoid doubt.
3) Any works of internal and external 'making good' required as a result of implementation of the works hereby approved shall be undertaken with materials and in a manner which are strictly compatible with, and fully maintaining, the traditional constructional detailing and character of the building, close-matching with existing materials as appropriate.

Reason: To ensure that the approved works are carried out in a manner that safeguards the historic character, detailing and appearance of this listed building in all respects (Section 16, NPPF)
4) Prior to work commencing full details of all external and internal materials, including specifications of metals, glazing, masonry and mortars as well as doors (including joinery) and ironmongery, shall be submitted to the local authority for approval. This should include all finishes and colours not agreed upon as well as materials for the rendered service yard boundary wall heightening.

Reason: To control the appearance of the development in the interests of preserving and enhancing the character and appearance of the Listed Building (NPPF Section 16).


Return to Search | Close WindowTop of Page