Conditions or Reasons for Planning Application - CB/24/03376/DOC
Conditions or Reasons:
19) Prior to commencement of development a report shall be submitted to and approved in writing by the Local Planning Authority demonstrating the geo-environmental risks associated with the construction of the development, including groundwater and potential subsidence which may impact the site and surroundings. The report shall include the following:-

1) Geotechnical surveys including but not limited to hydrogeology assessment, ground and stability testing and; ground percolation by a suitably qualified geotechnical engineer.

2) Based on the findings of 1) the report will set out a programme for the ongoing seasonal monitoring and mitigation of groundwater risks and ground movement during construction. This will take into account the influence of construction activities and of the interim drainage solutions (preceding the connection of the Anglian Water system and implementation of the surface water drainage system in full).

3) Any risks identified through 1) and 2) shall be monitored, mitigated and remediated including any groundwater/subsidence risks arising or created by the construction of the development within the site, its immediate vicinity and downstream and until the development is completed. Any correspondence, with Anglian Water or the Environment Agency should be provided to confirm any risks are managed in line with their requirements.

4) Any activities required to mitigate or remediate a risk associated with 3) is to be provided in writing to the Local Planning Authority for approval, or in the event of an emergency situation details are to be provided within 14 days. Pollution and/or contamination of groundwater is not permitted and all activities on site must ensure this is avoided. Any land drains or culvert within the site must be preserved and any damage to these remediated and no additional discharge introduced to these systems from the development site. The development shall be carried out strictly in accordance with the mitigation strategy as set out in the report and as approved in writing by the Local Planning Authority.

5) Prior to the completion of the development any temporary measures implemented parts 1-4 will be remediated and made good.

Reason: To restrict any development and ensure that the impact of groundwater flood risk is properly mitigated.
(Policy CC5 of the Local Plan, and Section 15 of the NPPF)