Conditions or Reasons for Planning Application - CB/24/03498/DOC
Conditions or Reasons:
2) No development shall take place until a Construction Environment Management Plan has been submitted and approved by the Local Planning Authority. The Construction Management Plan should include an outline of the proposed development, the sequencing of construction works and the management controls required with consideration of environmental effects. The scheme shall include:-

a) The location and arrangement of site access, compounds (including accommodation and cabins) and parking;
b) The use of hoardings and fencing (including temporary fencing);
c) The storage of construction materials and waste;
d) The handling and storage of topsoil (including imported topsoil);
e) Measures for the protection of existing vegetation and landscape areas (in accordance with BS5837:2012);
f) Permitted working hours and use of lighting, including a detailed lighting specification;
g) The implementation of planting (and where necessary proposed protection on the substantial completion of each phase); and
h) Responsibilities, and monitoring/reporting measures including supervision by appropriately qualified personnel.

All construction activities shall be implemented and maintained in accordance with the approved details and timing of the plan unless otherwise agreed in writing by the Local Planning Authority.

Reason: To ensure all impacts from development are taken into account and mitigated. (Section 15, NPPF)