Conditions or Reasons for Planning Application - CB/25/00549/DOC
Conditions or Reasons:
2) Notwithstanding the details submitted with the application, no development shall commence until details of the materials to be used for the external windows, doors, walls, roofs and rainwater goods of the proposed building/s have been submitted to and approved in writing by the Local Planning Authority. The development shall be carried out only in accordance with the approved details.
Reason: To ensure that the development is in keeping with the existing building. (Section 16, NPPF)
3) No development shall take place, until a schedule of works detailing all proposed repairs, re-instatement and making good to the fabric of the building has been submitted to and approved in writing by the Local Planning Authority. The development shall only be carried out only in accordance with the approved schedule of works. Details shall include a full and detailed specification of all materials to be used in the works.
Reason: To ensure that the special historical and architectural interest and integrity of the building is conserved and maintained.
(Section 16, NPPF)
4) No development shall take place until drawings of all new and proposed replacement windows and doors to a scale of 1:10 or 1:20, together with a specification of the materials and finishes has been submitted to and approved in writing by the Local Planning Authority. Details provided shall clearly show a section of the glazing bars, frame mouldings, door panels, the position of the door or window frame in relation to the face of the wall, the depth of the reveal and arch and sill details. The development shall be carried out only in accordance with the approved details.
Reason: To ensure that the proposed development/work is carried out in a manner that safeguards the historic character and appearance of the area.
(Section 16, NPPF)