| Conditions or Reasons for Planning Application - CB/25/02902/FULL |
| Conditions or Reasons: | 1)
The development hereby permitted shall begin not later than three years from the date of this permission.
Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
2)
The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers; 250819 - 001 A01, 250819 - 002 A03, 250819 - 003 A03, 250819 - 004 A03, 250819 - 006 A03, 250819 - 007 A02, 250819 - 008 A02, 250819 - 009 A02, 250819 - 010 A02, 250819 -020 A03.
Reason: To identify the approved plan/s and to avoid doubt. |
3)
All external works hereby permitted shall be carried out in materials to match as closely as possible in colour, type and texture, those of drawing numbers; 250819 - 007 A02, 250819 - 008 A02, 250819 - 009 A02, 250819 - 010 A02.
Reason: To safeguard the appearance of the completed development by ensuring that the development hereby permitted is finished externally with materials in the interests of the visual amenities of the locality. (Section 12, NPPF) |
|
|---|