<< Back to case
Conditions or Reasons for Planning Application - CB/25/03981/DOC
Conditions or Reasons:
2) The development hereby approved shall not commence until details of all external materials to be used in the development have been submitted to and approved in writing by the Local Planning
Authority. The development shall thereafter be carried out in accordance with the approved details.

Reason: To control the appearance of the development in the interests of the visual amenities of the locality and its location in the Chilterns AONB.
(Policy HQ1, CBLP July 2021, and Section 12 and 15, NPPF July 2021)
6) The development hereby approved shall not commence until details of a scheme of works on Land Park Lane, broadly in accordance with Drawing No.170-TA19 Revision A, have been submitted to and approved in writing by the Local Planning Authority. No dwelling shall be occupied until the scheme has been constructed in accordance with the approved details, amended as necessary by the technical and safety audit process, and opened to traffic.
Reason: In order to achieve safe and suitable access for all users.
(Policy T2, CBLP July 2021, and Section 9, NPPF July 2021)
22) The development hereby approved shall not commence until a detailed surface water drainage scheme, to manage surface water runoff from the development for up to and including the 1 in 100 year event (+40%CC), into deep bore soakage, and a maintenance and management plan for the scheme has been submitted to and approved in writing by the Local Planning Authority. Infiltration systems shall only be used where it can be demonstrated that they will not pose a risk to groundwater quality. The final detailed design shall be based on the agreed drainage Strategy (Ref: MAC 170-FRA-03 May 2021) and DEFRAs Non-statutory technical standards for sustainable drainage systems (March 2018) and shall be implemented and maintained as approved. Maintenance will ensure the system functions as designed for the lifetime of the development. Any variation to the connections and controls indicated on the approved drawing which may be necessary at the time of construction would require the resubmission of those details to the Local Planning Authority for approval.

Reason: To ensure the approved system will function to a satisfactory minimum standard of operation and maintenance and prevent the increased risk of flooding both on and off site. Infiltration through contaminated land has the potential to impact on groundwater quality.
(Policies CC3, CC5 and CC8, CBLP July 2021, and Sections 14 and 15, NPPF July 2021 and its supporting technical guidance)
23) Prior to the occupation of the dwellings hereby approved, the developer shall submit for the approval in writing of the Local Planning Authority a finalised 'Maintenance and Management Plan' for the entire surface water drainage system, inclusive of any adoption arrangements and/or private ownership or responsibilities, and confirmation that the approved surface water drainage scheme has been correctly and fully installed as per the final approved details.
Reason: To ensure that the implementation and long term operation of a sustainable drainage system (SuDS) is in line with what has been approved.
(Policies CC3 and CC5, CBLP July 2021, and Section 14, NPPF July 2021 and its supporting technical guidance)
29) The development hereby approved shall not commence until a plan showing the locations of fire hydrants within the site to ensure that no dwelling is further than 90m from the nearest hydrant shall be submitted to and approved in writing by the Local Planning Authority. No dwellings shall be occupied until the fire hydrants have been installed, and shall thereafter be retained.

Reason: To protect the amenity of future occupants of the proposed flats.
(Policy HQ1, CBLP July 2021, and Section 12, NPPF July 2021)


Return to Search | Close WindowTop of Page