Conditions or Reasons:
2) No above ground development shall take place, notwithstanding the details submitted with the application, until details of the materials to be used for the external walls and roofs of the development hereby approved have been submitted to and approved in writing by the Local Planning Authority. The development shall thereafter be carried out in accordance with the approved details.

Reason: To control the appearance of the non-designated heritage asset in the interests of the visual amenities of the locality.
(Section 12, NPPF)
5) No development approved by this permission shall take place until a Phase 2 site investigation has been undertaken and a detailed report of the findings submitted, in accordance with the recommendations of the Paddock Geoengineering Preliminary Contamination Risk Assessment report dated March 2020 (Ref: P20-034pra_v2), has been submitted to and approved in writing by the Local Planning Authority. Where found to be necessary by the phase 2 report a remediation strategy to deal with the risks associated with contamination of the site shall also be submitted to and approved in writing by the Local Planning Authority. The remediation strategy shall include an options appraisal giving full details of the remediation measures required and how they are to be undertaken. The strategy shall include a plan providing details of how the remediation works shall be judged to be complete and arrangements for contingency action.

Reason:

In the interests of protecting human health and the environment (policy CC8, Central Bedfordshire Local Plan).
17) Prior to commencement of the development, a noise assessment shall be submitted to the Council for approval of external noise levels including. reflected and re-radiated noise and details of the sound insulation of the building envelope, and of acoustically attenuated mechanical ventilation as necessary to achieve internal room- and (if provided) external amenity noise standards in accordance with the criteria of BS8233:2014. The approved details shall be implemented prior to occupation of the development and thereafter be permanently retained.

Reason: In the interests of acceptable living conditions for future occupiers of the dwelling (policy HQ1, Central Bedfordshire Local Plan, 2021).