Informative Notes: | 1
)The applicant is advised that no works associated with the construction of the vehicular access should be carried out within the confines of the public highway without prior consent, in writing, of the Central Bedfordshire Council. Upon receipt of this Notice of Planning Approval, the applicant is advised to write to Central Bedfordshire Council's, Highways Help Desk P.O.Box 1395, Bedford, MK42 5AN quoting the Planning Application number and supplying a copy of the Decision Notice and a copy of the approved plan. This will enable the necessary consent and procedures under Section 184 of the Highways Act to be implemented. The applicant is also advised that if any of the works associated with the construction of the vehicular access affects or requires the removal and/or the relocation of any equipment, apparatus or structures (e.g. street name plates, bus stop signs or shelters, statutory authority equipment etc.) then the applicant will be required to bear the cost of such removal or alteration.The applicant is advised that no works associated with the construction of the vehicular access should be carried out within the confines of the public highway without prior consent, in writing, of the Central Bedfordshire Council. Upon receipt of this Notice of Planning Approval, the applicant is advised to write to Central Bedfordshire Council's, Highways Help Desk P.O.Box 1395, Bedford, MK42 5AN quoting the Planning Application number and supplying a copy of the Decision Notice and a copy of the approved plan. This will enable the necessary consent and procedures under Section 184 of the Highways Act to be implemented. The applicant is also advised that if any of the works associated with the construction of the vehicular access affects or requires the removal and/or the relocation of any equipment, apparatus or structures (e.g. street name plates, bus stop signs or shelters, statutory authority equipment etc.) then the applicant will be required to bear the cost of such removal or alteration. |
2
)The applicant is advised that in order to comply with Condition 13 of this permission it will be necessary for the developer of the site to enter into an agreement with Central Bedfordshire Council as Highway Authority under Section 278 of the Highways Act 1980 to ensure the satisfactory completion of the access and associated road improvements. Further details can be obtained from the Highways Development Control Group, Development Management Division, , Central Bedfordshire Council, P.O. Box 1395, Bedford, MK42 5ANThe applicant is advised that in order to comply with Condition 13 of this permission it will be necessary for the developer of the site to enter into an agreement with Central Bedfordshire Council as Highway Authority under Section 278 of the Highways Act 1980 to ensure the satisfactory completion of the access and associated road improvements. Further details can be obtained from the Highways Development Control Group, Development Management Division, , Central Bedfordshire Council, P.O. Box 1395, Bedford, MK42 5AN |
3
)The applicant is advised that no highway surface water drainage system designed as part of the new development, will be allowed to enter any existing highway surface water drainage system without the applicant providing evidence that the existing system has sufficient capacity to account for any highway run off generated by that development. Existing highway surface water drainage systems may be improved at the developers expense to account for extra surface water generated .Any improvements must be approved by the Highways Development Control group, Development Management Division, Central Bedfordshire Council. Further details can be obtained from the Traffic Management group Highways and Transport Division, Central Bedfordshire Council, P.O. Box 1395 Bedford, MK42 5AN.The applicant is advised that no highway surface water drainage system designed as part of the new development, will be allowed to enter any existing highway surface water drainage system without the applicant providing evidence that the existing system has sufficient capacity to account for any highway run off generated by that development. Existing highway surface water drainage systems may be improved at the developers expense to account for extra surface water generated .Any improvements must be approved by the Highways Development Control group, Development Management Division, Central Bedfordshire Council. Further details can be obtained from the Traffic Management group Highways and Transport Division, Central Bedfordshire Council, P.O. Box 1395 Bedford, MK42 5AN. |
4
)The applicant is advised that the requirements of the New Roads and Street Works Act 1991 will apply to any works undertaken within the limits of the existing public highway. Further details can be obtained from the Traffic Management group Highways and Transportation Division, Central Bedfordshire Council, P.O. Box 1395 Bedford, MK42 5AN.The applicant is advised that the requirements of the New Roads and Street Works Act 1991 will apply to any works undertaken within the limits of the existing public highway. Further details can be obtained from the Traffic Management group Highways and Transportation Division, Central Bedfordshire Council, P.O. Box 1395 Bedford, MK42 5AN. |
5
)The applicant is advised that the closure of existing access shall include the reinstatement of the highway to include any footway, verge and kerbing in a manner to be agreed in writing with Central Bedfordshire Council's, Highways Help Desk P.O.Box 1395, Bedford, MK42 5AN. No work shall be carried out within the confines of the public highway without prior consent. The applicant will also be expected to bear all costs involved in closing the access.The applicant is advised that the closure of existing access shall include the reinstatement of the highway to include any footway, verge and kerbing in a manner to be agreed in writing with Central Bedfordshire Council's, Highways Help Desk P.O.Box 1395, Bedford, MK42 5AN. No work shall be carried out within the confines of the public highway without prior consent. The applicant will also be expected to bear all costs involved in closing the access. |
6
)You are advised to note the comments of the Waste Officer who states that the cost of bins for this development will be chargeable to the applicant.You are advised to note the comments of the Waste Officer who states that the cost of bins for this development will be chargeable to the applicant. |
7
)You are advised to note that condition 10 relating to surface water drainage could result in a development that cannot immediately be implemented either because it may not be possible to provide adequate details to discharge such a condition or because it could result in drainage works which in themselves require formal planning consent.You are advised to note that condition 10 relating to surface water drainage could result in a development that cannot immediately be implemented either because it may not be possible to provide adequate details to discharge such a condition or because it could result in drainage works which in themselves require formal planning consent. |
|
---|