1. Return to Search Page >>2. Search Results >>3. Planning Application Detail
Details of Planning Application - CB/13/02618/FULL

Click on the Consultation link below for neighbour and statutory consultee information and to comment on this application. Ensure your opinions are received before the consultation closing date.


Application Details View Documents (opens in new window) Consultation
Application registeredConsultation periodAwaiting decisionDecidedAppealAppeal decided
Application Type:Full Application
Date Received:26 / 07 / 2013
Registration (Validation) Date:20 / 08 / 2013
Consultation Start Date:20 / 08 / 2013
Earliest Decision Date (Consultation Period Expires):24 / 09 / 2013
Target Date for Decision:15 / 10 / 2013
Location:10A Dunstable Road, Houghton Regis, Dunstable, LU5 5DB
Parish Name:Houghton Regis
Conservation Area:Not Applicable
Listed Building Grade:Not available
Environmental Assessment:Not available
Expected Decision Level:Officer Delegated
Description:Renew expired planning permission for a one bedroom conversion from commercial building to domestic use
Case Officer:Donna Lavender
Case Officer Tel:0300 300 5095
Case Officer Email:donna.lavender@centralbedfordshire.gov.uk
Status:Decided
Agent:Kingsley Griffiths
18 Matthew Street
Dunstable
Beds
LU6 1SD
Press Date:No date
Site Notice Date:No date
NeighboursResponses Received: 0
and Representatives:In Favour: 0
Representation DetailsAgainst: 0
Comments: 0
Petitions Against: 0
Petitions For: 0
Officer Site Visit Date:27/09/2013
Committee Site Visit Date:No date
Committee Meeting Date:No date
Decision Level:Officer Delegated
Date Decision Made:07 / 10 / 2013
Date Decision Despatched:08 / 10 / 2013
Decision:Full Application - Granted
Conditions or Reasons:View Conditions or Reasons
Informative Notes:
1 )In accordance with Article 31 of the Town and Country Planning (Development Management Procedure) (England) Order 2010, the reason for any condition above relates to the Policies as referred to in the South Bedfordshire Local Plan Review (SBLPR) and the emerging Development Strategy for Central Bedfordshire (DSCB).In accordance with Article 31 of the Town and Country Planning (Development Management Procedure) (England) Order 2010, the reason for any condition above relates to the Policies as referred to in the South Bedfordshire Local Plan Review (SBLPR) and the emerging Development Strategy for Central Bedfordshire (DSCB).
2 )This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority.This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority.
3 )Where remediation measures are necessary a Remediation Strategy shall be provided giving full details of the remediation measures required and how they are to be undertaken. On completion of those works a verification report shall be provided confirming the remediation measures that have been undertaken in accordance with the Remediation Strategy and setting out measure for further monitoring and reporting as necessary.Where remediation measures are necessary a Remediation Strategy shall be provided giving full details of the remediation measures required and how they are to be undertaken. On completion of those works a verification report shall be provided confirming the remediation measures that have been undertaken in accordance with the Remediation Strategy and setting out measure for further monitoring and reporting as necessary.
4 )If, during development, contamination not previously identified is found to be present at the site, no further development (unless agreed in writing with the Local Planning Authority) shall be carried out until the developer has submitted a Remediation Strategy or obtained written approval from the Local Planning Authority for an addendum to an existing Remediation Strategy, the addendum of which must detail how this unsuspected contamination shall be dealt with and from the date of approval of the addendums shall form part of the Remediation Strategy.If, during development, contamination not previously identified is found to be present at the site, no further development (unless agreed in writing with the Local Planning Authority) shall be carried out until the developer has submitted a Remediation Strategy or obtained written approval from the Local Planning Authority for an addendum to an existing Remediation Strategy, the addendum of which must detail how this unsuspected contamination shall be dealt with and from the date of approval of the addendums shall form part of the Remediation Strategy.
5 )Where remedial measures are necessary, they should be managed with Part IIA of the Environmental Protection Act 1990 in mind. Encapsulation of any contaminants should be made on the risk-based assessment so that they are unlikely to be subject to future release to the environment. All ground investigations shall be risk based and have regard to BS10175:2001 Investigation of Potentially Contaminated Sites - Code of Practice and Environment Agency/NHBC R&D Publication 66 - Guidance for the Safe Development of Housing on Land Affected by Contamination. Where analyses are undertaken analytical laboratories should be accredited to MCERTS and where appropriate laboratory methods should also be accredited to MCERTS. The applicants/agent's consulting engineers shall certify that decontamination and remediation of the site has been undertaken in accordance with any measures approved by the Local Planning Authority. The applicant shall advise the Local Planning Authority of commencement of the works. The applicant should also be made aware that the ownership of land shown to be contaminated may accrue legal and financial liabilities under Part IIA of the Environmental Protection Act 1990. Such liabilities are maximised when "pollutant linkages" engender "pathways" for the contaminants to reach "receptors". Central Bedfordshire Council has published its Contaminated Land Inspection Strategy in line with the Environmental Protection Act 1990: Part IIA and its definition thereof. No land has yet been formally designated as being 'contaminated'. However, it should not be taken to imply that the property or adjoining land is free from contamination.Where remedial measures are necessary, they should be managed with Part IIA of the Environmental Protection Act 1990 in mind. Encapsulation of any contaminants should be made on the risk-based assessment so that they are unlikely to be subject to future release to the environment. All ground investigations shall be risk based and have regard to BS10175:2001 Investigation of Potentially Contaminated Sites - Code of Practice and Environment Agency/NHBC R&D Publication 66 - Guidance for the Safe Development of Housing on Land Affected by Contamination. Where analyses are undertaken analytical laboratories should be accredited to MCERTS and where appropriate laboratory methods should also be accredited to MCERTS. The applicants/agent's consulting engineers shall certify that decontamination and remediation of the site has been undertaken in accordance with any measures approved by the Local Planning Authority. The applicant shall advise the Local Planning Authority of commencement of the works. The applicant should also be made aware that the ownership of land shown to be contaminated may accrue legal and financial liabilities under Part IIA of the Environmental Protection Act 1990. Such liabilities are maximised when "pollutant linkages" engender "pathways" for the contaminants to reach "receptors". Central Bedfordshire Council has published its Contaminated Land Inspection Strategy in line with the Environmental Protection Act 1990: Part IIA and its definition thereof. No land has yet been formally designated as being 'contaminated'. However, it should not be taken to imply that the property or adjoining land is free from contamination.
6 )This permission is subject to a Legal Obligation under Section 106 of the Town and Country Planning Act 1990.This permission is subject to a Legal Obligation under Section 106 of the Town and Country Planning Act 1990.
Appeal Received Date:This case has no appeals against it
Planning Obligation Status:Not available

Return to Search PageTop of Page