| Details of Planning Application -
CB/17/02417/RM |
| Application registered | Consultation period | Awaiting decision | Decided | Appeal | Appeal decided |
|
|---|
| Application Type: | Reserved Matters |
|---|
| Date Received: | 16
/
05
/
2017 |
|---|
| Registration (Validation) Date: | 09
/
06
/
2017 |
|---|
| Consultation Start Date: | 09
/
06
/
2017 |
|---|
| Earliest Decision Date (Consultation Period Expires): | 30
/
10
/
2017 |
|---|
| Target Date for Decision: | 08
/
09
/
2017 |
|---|
| Location: | Land adjacent to St Marys (Stotfold) Lower School, Rook Tree Lane, Stotfold, Hitchin SG5 4DJ |
|---|
| Parish Name: | Stotfold |
|---|
| Conservation Area: | Not available |
|---|
| Listed Building Grade: | Not available |
|---|
| Environmental Assessment: | Not available |
|---|
| Expected Decision Level: | Not available |
|---|
| Description: | Reserved Matters - Appearance, landscaping, layout and scale for 15 dwellings Application No CB/16/01148/OUT dated 08/09/2016 |
|---|
| Case Officer: | Donna Lavender |
|---|
| Case Officer Tel: | 0300 300 5095 |
|---|
| Case Officer Email: | donna.lavender@centralbedfordshire.gov.uk |
|---|
| Status: | Decided |
|---|
| Agent: | Mr Alistair McIntyre |
|---|
| 1 Cantelupe Court |
|---|
| De La Warr Parade |
|---|
| Bexhill on Sea |
|---|
| TN40 1JY |
|---|
| Press Date: | 30
/
06
/
2017 |
|---|
| Site Notice Date: | 17
/
07
/
2017 |
|---|
| Neighbours | Responses Received:
9 |
|---|
| and Representatives: | In Favour:
0 |
|---|
| Representation Details | Against:
6 |
|---|
| Comments:
3 |
|---|
| Petitions Against:
0 |
|---|
| Petitions For:
0 |
|---|
| Officer Site Visit Date: | 17/07/2017 |
|---|
| Committee Site Visit Date: | No date |
|---|
| Committee Meeting Date: | 08
/
11
/
2017 |
|---|
| Decision Level: | Development Management Committee |
|---|
| Date Decision Made: | 08
/
11
/
2017 |
|---|
| Date Decision Despatched: | 09
/
11
/
2017 |
|---|
| Decision: | Reserved Matters- Granted |
|---|
| Conditions or Reasons: | View Conditions or Reasons |
|---|
| Informative Notes: | | 1
)In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the National Planning Policy Framework (NPPF) and the Core Strategy for North Central Bedfordshire.In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the National Planning Policy Framework (NPPF) and the Core Strategy for North Central Bedfordshire. |
| 2
)This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority.This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority. |
| 3
)Anglian Water has assets close to or crossing this site or there are assets subject to an adoption agreement. Therefore the site layout should take this into account and accommodate those assets within either prospectively adoptable highways or public open space. If this is not practicable then the sewers will need to be diverted at the developers cost under Section 185 of the Water Industry Act 1991. or, in the case of apparatus under an adoption agreement, liaise with the owners of the apparatus. It should be noted that the diversion works should normally be completed before development can commence.Anglian Water has assets close to or crossing this site or there are assets subject to an adoption agreement. Therefore the site layout should take this into account and accommodate those assets within either prospectively adoptable highways or public open space. If this is not practicable then the sewers will need to be diverted at the developers cost under Section 185 of the Water Industry Act 1991. or, in the case of apparatus under an adoption agreement, liaise with the owners of the apparatus. It should be noted that the diversion works should normally be completed before development can commence. |
| 4
)The applicant is advised to be mindful of the fact that the land is subject to a number of obligations by legal agreements. A Section 106 agreement for the outline planning permission under reference CB/16/01448/OUT.The applicant is advised to be mindful of the fact that the land is subject to a number of obligations by legal agreements. A Section 106 agreement for the outline planning permission under reference CB/16/01448/OUT. |
| 5
)The applicant is advised that in order to comply with highways matters of this permission it will be necessary for the developer of the site to enter into an agreement with Central Bedfordshire Council as Highway Authority under Section 278 of the Highways Act 1980 to ensure the satisfactory completion of the access and associated road improvements. Further details can be obtained from the Development Management Group, Central Bedfordshire Council, Priory House, Monks Walk, Chicksands, Shefford SG17 5TQ.The applicant is advised that in order to comply with highways matters of this permission it will be necessary for the developer of the site to enter into an agreement with Central Bedfordshire Council as Highway Authority under Section 278 of the Highways Act 1980 to ensure the satisfactory completion of the access and associated road improvements. Further details can be obtained from the Development Management Group, Central Bedfordshire Council, Priory House, Monks Walk, Chicksands, Shefford SG17 5TQ. |
| 6
)The applicant is advised that the following conditions on the outline planning permission are pre commencement and still require discharge:
6. Landscape Management Plan (which should include the SuDs management or any shared provisions such as open space, visitor areas etc)
10.Sustainability Measures
11. RemediationThe applicant is advised that the following conditions on the outline planning permission are pre commencement and still require discharge:
6. Landscape Management Plan (which should include the SuDs management or any shared provisions such as open space, visitor areas etc)
10.Sustainability Measures
11. Remediation |
|
|---|
| Appeal Received Date: | This case has no appeals against it |
|---|
| Planning Obligation Status: | Not available |
|---|