| Details of Planning Application -
CB/17/02595/ADV |
| Application registered | Consultation period | Awaiting decision | Decided | Appeal | Appeal decided |
|
|---|
| Application Type: | Advertisement |
|---|
| Date Received: | 24
/
05
/
2017 |
|---|
| Registration (Validation) Date: | 24
/
05
/
2017 |
|---|
| Consultation Start Date: | 24
/
05
/
2017 |
|---|
| Earliest Decision Date (Consultation Period Expires): | 17
/
07
/
2017 |
|---|
| Target Date for Decision: | 19
/
07
/
2017 |
|---|
| Location: | Pylon House, Bedford Road, Marston Moretaine, Bedford, MK43 0LA |
|---|
| Parish Name: | Marston Moreteyne |
|---|
| Conservation Area: | Not available |
|---|
| Listed Building Grade: | Not available |
|---|
| Environmental Assessment: | Not available |
|---|
| Expected Decision Level: | Officer Delegated |
|---|
| Description: | Advertisement Consent: 1 off externally illuminated fascia sign 1 off externally illuminated totem. |
|---|
| Case Officer: | Judy Martin |
|---|
| Case Officer Tel: | 0300 300 4375 |
|---|
| Case Officer Email: | judy.martin@centralbedfordshire.gov.uk |
|---|
| Status: | Decided |
|---|
| Agent: | Miss K Nash |
|---|
| Units 3-4 Arden Park |
|---|
| Arden Road |
|---|
| Frankley |
|---|
| Birmingham |
|---|
| B45 0JA |
|---|
| Press Date: | No date |
|---|
| Site Notice Date: | 26
/
06
/
2017 |
|---|
| Neighbours | Responses Received:
0 |
|---|
| and Representatives: | In Favour:
0 |
|---|
| Representation Details | Against:
0 |
|---|
| Comments:
0 |
|---|
| Petitions Against:
0 |
|---|
| Petitions For:
0 |
|---|
| Officer Site Visit Date: | 26/06/2017 |
|---|
| Committee Site Visit Date: | No date |
|---|
| Committee Meeting Date: | No date |
|---|
| Decision Level: | Officer Delegated |
|---|
| Date Decision Made: | 18
/
07
/
2017 |
|---|
| Date Decision Despatched: | 19
/
07
/
2017 |
|---|
| Decision: | Advertisement - Granted |
|---|
| Conditions or Reasons: | View Conditions or Reasons |
|---|
| Informative Notes: | | 1
)The applicant is advised that the requirements of the New Roads and Street Works Act 1991 will apply to any works undertaken within the limits of the existing public highway. Further details can be obtained from the Highways Help Desk tel: 0300 300 8049The applicant is advised that the requirements of the New Roads and Street Works Act 1991 will apply to any works undertaken within the limits of the existing public highway. Further details can be obtained from the Highways Help Desk tel: 0300 300 8049 |
| 2
)The applicant is advised that parking for contractor's vehicles and the storage of materials associated with this development should take place within the site and not extend into within the public highway without authorisation from the highway authority. If necessary the applicant is advised to contact Central Bedfordshire Council's Highway Help Desk on 03003008049. Under the provisions of the Highways Act 1980 the developer may be liable for any damage caused to the public highway as a result of construction of the development hereby approvedThe applicant is advised that parking for contractor's vehicles and the storage of materials associated with this development should take place within the site and not extend into within the public highway without authorisation from the highway authority. If necessary the applicant is advised to contact Central Bedfordshire Council's Highway Help Desk on 03003008049. Under the provisions of the Highways Act 1980 the developer may be liable for any damage caused to the public highway as a result of construction of the development hereby approved |
| 3
)The contractor and / or client are to ensure that any mud or building material debris such as sand, cement or concrete that is left on the public highway, or any mud arising from construction vehicular movement, shall be removed immediately and in the case of concrete, cement, mud or mortar not allowed to dry on the highwayThe contractor and / or client are to ensure that any mud or building material debris such as sand, cement or concrete that is left on the public highway, or any mud arising from construction vehicular movement, shall be removed immediately and in the case of concrete, cement, mud or mortar not allowed to dry on the highway |
|
|---|
| Appeal Received Date: | This case has no appeals against it |
|---|
| Planning Obligation Status: | Not available |
|---|