Details of Planning Application - CB/18/01696/RM

Click on the Consultation link below for neighbour and statutory consultee information and to comment on this application. Ensure your opinions are received before the consultation closing date.


Application Details View Documents (opens in new window) Consultation
Application registeredConsultation periodAwaiting decisionDecidedAppealAppeal decided
Application Type:Reserved Matters
Date Received:20 / 04 / 2018
Registration (Validation) Date:23 / 04 / 2018
Consultation Start Date:23 / 04 / 2018
Earliest Decision Date (Consultation Period Expires):06 / 08 / 2018
Target Date for Decision:23 / 07 / 2018
Location:Brickyard Quarry, Grovebury Road, Leighton Buzzard, LU7 4SQ
Parish Name:Leighton-Linslade
Conservation Area:Not available
Listed Building Grade:Not available
Environmental Assessment:Not available
Expected Decision Level:Officer Delegated
Description:Reserved matters application for appearance, landscaping, layout and scale of 165 dwellings and associated parking and open space, pursuant to outline planning consent CB/11/00501/OUT dated 19.08.2011 and variation of condition CB/16/03224/VOC dated 04.08.2017
Case Officer:Debbie Quinn
Case Officer Tel:0300 300 5723
Case Officer Email:debbie.quinn@centralbedfordshire.gov.uk
Status:Decided
Agent:Miss Cocuccioni
26 Finsbury Square
London
EC2A 1DS
Press Date:29 / 05 / 2018
Site Notice Date:21 / 05 / 2018
NeighboursResponses Received: 18
and Representatives:In Favour: 0
Representation DetailsAgainst: 16
Comments: 1
Petitions Against: 1
Petitions For: 0
Officer Site Visit Date:21/05/2018
Committee Site Visit Date:No date
Committee Meeting Date:No date
Decision Level:Officer Delegated
Date Decision Made:23 / 07 / 2018
Date Decision Despatched:23 / 07 / 2018
Decision:Reserved Matters- Granted
Conditions or Reasons:View Conditions or Reasons
Informative Notes:
1 )In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the South Bedfordshire Local Plan Review (SBLPR) and the National Planning Policy Framework (NPPF).In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the South Bedfordshire Local Plan Review (SBLPR) and the National Planning Policy Framework (NPPF).
2 )This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority.This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority.
3 )Status of Conditions attached to the Outline Planning permission CB/16/03224/VOC The following conditions are considered to be discharged by this approval of reserved matters: 1, 5, 21, 25, 28, 29 and 33. Condition 17 is partially discharged by this approval of reserved matters, however, the condition also contains a requirement for post-completion validation monitoring, with the results to be submitted to the Local Planning Authority prior to occupation. Conditions 7, 18, 24, and 31 have already been complied with or are no longer applicable. The following conditions still need to be discharged: 3, 4, 6, 8, 9, 13, 14, 15, 16, 22, 26, 27, 30 and 32. The following conditions only require discharging in certain circumstances: 10, 11 and 12. All other conditions are instructive and do not require formal discharge, although they will need to be complied with.Status of Conditions attached to the Outline Planning permission CB/16/03224/VOC The following conditions are considered to be discharged by this approval of reserved matters: 1, 5, 21, 25, 28, 29 and 33. Condition 17 is partially discharged by this approval of reserved matters, however, the condition also contains a requirement for post-completion validation monitoring, with the results to be submitted to the Local Planning Authority prior to occupation. Conditions 7, 18, 24, and 31 have already been complied with or are no longer applicable. The following conditions still need to be discharged: 3, 4, 6, 8, 9, 13, 14, 15, 16, 22, 26, 27, 30 and 32. The following conditions only require discharging in certain circumstances: 10, 11 and 12. All other conditions are instructive and do not require formal discharge, although they will need to be complied with.
4 )The Flood Risk Management Team have provided the following advice in relation to the discharge of conditions 13 and 14: 1. The final detailed design including proposed standards of operation, construction, structural integrity and ongoing maintenance must be compliant with the 'Non-statutory technical standards for sustainable drainage systems' (March 2015, Ref: PB14308), 'Central Bedfordshire Sustainable Drainage Guidance' (Adopted April 2014, Updated May 2015), and recognised best practise including the Ciria SuDS Manual (2016, C753). 2. To ensure future and subsequent homeowners will be aware of any maintenance requirements / responsibilities for surface water drainage; further measures should be proposed by the applicant and may include, for example, information provided to the first purchaser of the property and also designation/registration of the SuDS so that it appears as a Land Charge for the property and as such is identified to subsequent purchasers of the property. 3. Land drainage Consent under the Land Drainage Act 1991 must be secured to discharge surface water and details of this provided with the full detailed design. An easement should be provided on the developable side of the watercourse to allow for access for maintenance, this should be 9m but may depend on the maintenance requirements considered appropriate.The Flood Risk Management Team have provided the following advice in relation to the discharge of conditions 13 and 14: 1. The final detailed design including proposed standards of operation, construction, structural integrity and ongoing maintenance must be compliant with the 'Non-statutory technical standards for sustainable drainage systems' (March 2015, Ref: PB14308), 'Central Bedfordshire Sustainable Drainage Guidance' (Adopted April 2014, Updated May 2015), and recognised best practise including the Ciria SuDS Manual (2016, C753). 2. To ensure future and subsequent homeowners will be aware of any maintenance requirements / responsibilities for surface water drainage; further measures should be proposed by the applicant and may include, for example, information provided to the first purchaser of the property and also designation/registration of the SuDS so that it appears as a Land Charge for the property and as such is identified to subsequent purchasers of the property. 3. Land drainage Consent under the Land Drainage Act 1991 must be secured to discharge surface water and details of this provided with the full detailed design. An easement should be provided on the developable side of the watercourse to allow for access for maintenance, this should be 9m but may depend on the maintenance requirements considered appropriate.
5 )The Waste Services Team has provided the following advice: The Council's waste collection pattern for Leighton Buzzard is as follows: Week 1 1 x 240 litre residual waste wheelie bin Week 2 1 x 240 litre recycling wheelie bin, 1 x 240 litre garden waste wheelie bin Please note that there is a contribution to pay for the supply/delivery of the bins. Our current charges for this are: 240l - £25 +VAT per bin 360l - £35 + VAT per bin 660l - £250 + VAT per bin 1100l - £350 + VAT per bin This must be paid prior to discharging the relevant condition. A purchase order must be raised for the quantity of bins required and sent to Waste Services quoting the relevant planning reference number. We will also require a map of the site detailing street names, plot and house numbers. Please also refer to the Design Guide as the Council will not be able to supply waste collections where the bin and access requirements do not meet our contractual provision: http://www.centralbedfordshire.gov.uk/planning/design/info.aspxThe Waste Services Team has provided the following advice: The Council's waste collection pattern for Leighton Buzzard is as follows: Week 1 1 x 240 litre residual waste wheelie bin Week 2 1 x 240 litre recycling wheelie bin, 1 x 240 litre garden waste wheelie bin Please note that there is a contribution to pay for the supply/delivery of the bins. Our current charges for this are: 240l - £25 +VAT per bin 360l - £35 + VAT per bin 660l - £250 + VAT per bin 1100l - £350 + VAT per bin This must be paid prior to discharging the relevant condition. A purchase order must be raised for the quantity of bins required and sent to Waste Services quoting the relevant planning reference number. We will also require a map of the site detailing street names, plot and house numbers. Please also refer to the Design Guide as the Council will not be able to supply waste collections where the bin and access requirements do not meet our contractual provision: http://www.centralbedfordshire.gov.uk/planning/design/info.aspx
6 )The scheme for the LEAP will need to be approved as part of the submission to discharge condition 30 of permission CB/16/03224/VOC. The applicant is advised that the LEAP shown on submitted drawing no. 6580.PSP.ASP2.2 Revision A should be augmented by the addition of a Proludic J2581 Cableway.The scheme for the LEAP will need to be approved as part of the submission to discharge condition 30 of permission CB/16/03224/VOC. The applicant is advised that the LEAP shown on submitted drawing no. 6580.PSP.ASP2.2 Revision A should be augmented by the addition of a Proludic J2581 Cableway.
Appeal Received Date:This case has no appeals against it
Planning Obligation Status:Not available