Details of Planning Application -
CB/19/02117/PAAD |
Application registered | Consultation period | Awaiting decision | Decided | Appeal | Appeal decided |
|
---|
Application Type: | P.Notif. Agricultural to Dwelling |
---|
Date Received: | 26
/
06
/
2019 |
---|
Registration (Validation) Date: | 04
/
07
/
2019 |
---|
Consultation Start Date: | 04
/
07
/
2019 |
---|
Earliest Decision Date (Consultation Period Expires): | 06
/
08
/
2019 |
---|
Target Date for Decision: | 29
/
08
/
2019 |
---|
Location: | Old Farm, Sheep Lane, Potsgrove, Milton Keynes, MK17 9HQ |
---|
Parish Name: | Potsgrove |
---|
Conservation Area: | Not available |
---|
Listed Building Grade: | Not available |
---|
Environmental Assessment: | Not available |
---|
Expected Decision Level: | Not available |
---|
Description: | Prior Notification of Change of Use of Agricultural building to two one bedroom residential units. |
---|
Case Officer: | Mark Spragg |
---|
Case Officer Tel: | 0300 300 5796 |
---|
Case Officer Email: | mark.spragg3@centralbedfordshire.gov.uk |
---|
Status: | Decided |
---|
Agent: | Mr Robert Gooding |
---|
| 11 Saracen Way |
---|
| Newark Road |
---|
| Peterborough |
---|
| PE1 5WS |
---|
Press Date: | No date |
---|
Site Notice Date: | No date |
---|
Neighbours | Responses Received:
0 |
---|
and Representatives: | In Favour:
0 |
---|
Representation Details | Against:
0 |
---|
| Comments:
0 |
---|
| Petitions Against:
0 |
---|
| Petitions For:
0 |
---|
Officer Site Visit Date: | 11/07/2019 |
---|
Committee Site Visit Date: | No date |
---|
Committee Meeting Date: | No date |
---|
Decision Level: | Officer Delegated |
---|
Date Decision Made: | 20
/
08
/
2019 |
---|
Date Decision Despatched: | 20
/
08
/
2019 |
---|
Decision: | Prior Approval - Approved Change Of Use |
---|
Conditions or Reasons: | View Conditions or Reasons |
---|
Informative Notes: | 1
) If during any site investigation, excavation, engineering or construction works evidence of land contamination is identified, the applicant shall notify the Local Planning Authority without delay. Any land contamination identified shall be remediated to the satisfaction of the Local Planning Authority to ensure that the site is made suitable for its end use. If during any site investigation, excavation, engineering or construction works evidence of land contamination is identified, the applicant shall notify the Local Planning Authority without delay. Any land contamination identified shall be remediated to the satisfaction of the Local Planning Authority to ensure that the site is made suitable for its end use. |
2
)The applicant is advised of the Bedfordshire Fire and Rescue Service comments below and the need to meet Building Control Regfulations in respect of Fire Safety.
"We have identified that the location of your site could make it impractical for fire hydrants to be installed. Having completed a risk based assessment of the proposed site and the available water supplies for firefighting, we would consider the installation of domestic sprinklers as an alternative to the installation of a fire hydrant".The applicant is advised of the Bedfordshire Fire and Rescue Service comments below and the need to meet Building Control Regfulations in respect of Fire Safety.
"We have identified that the location of your site could make it impractical for fire hydrants to be installed. Having completed a risk based assessment of the proposed site and the available water supplies for firefighting, we would consider the installation of domestic sprinklers as an alternative to the installation of a fire hydrant". |
|
---|
Appeal Received Date: | This case has no appeals against it |
---|
Planning Obligation Status: | Not available |
---|