| Informative Notes: | | 1
)The applicant and the developer are advised that this permission is subject to a legal obligation under Section 106 of the Town and Country Planning Act 1990.The applicant and the developer are advised that this permission is subject to a legal obligation under Section 106 of the Town and Country Planning Act 1990. |
| 2
)The applicant is advised that in order to comply with Condition 5 of this permission it will be necessary for the developer of the site to enter into an agreement with Central Bedfordshire Council as Highway Authority under Section 278 of the Highways Act 1980 to ensure the satisfactory completion of the access and associated road improvements. You are advised to contact the Highways Agreements Officer, Community Services, Central Bedfordshire Council, Priory House, Monks Walk, Chicksands, Shefford SG17 5TQ. E-mail highwaysagreements@centralbedfordshire.gov.ukThe applicant is advised that in order to comply with Condition 5 of this permission it will be necessary for the developer of the site to enter into an agreement with Central Bedfordshire Council as Highway Authority under Section 278 of the Highways Act 1980 to ensure the satisfactory completion of the access and associated road improvements. You are advised to contact the Highways Agreements Officer, Community Services, Central Bedfordshire Council, Priory House, Monks Walk, Chicksands, Shefford SG17 5TQ. E-mail highwaysagreements@centralbedfordshire.gov.uk |
| 3
)The applicant is advised that the requirements of the New Roads and Street Works Act 1991 will apply to any works undertaken within the limits of the existing public highway. Further details can be obtained by contacting The Street Works Co-ordinator, Central Bedfordshire Highways, by contacting the Highways Helpdesk 0300 300 8301. The applicant is advised that parking for contractor's vehicles and the storage of materials and deliveries associated with this development should take place within the site and not extend into within the public highway without authorisation from the highway authority. If necessary the applicant is advised to contact The Street Works Co-ordinator, Central Bedfordshire Highways, by contacting the Highways Helpdesk 0300 300 8301. Under the provisions of the Highways Act 1980 the developer may be liable for any damage caused to the public highway as a result of demolition/construction of the development hereby approved.The applicant is advised that the requirements of the New Roads and Street Works Act 1991 will apply to any works undertaken within the limits of the existing public highway. Further details can be obtained by contacting The Street Works Co-ordinator, Central Bedfordshire Highways, by contacting the Highways Helpdesk 0300 300 8301. The applicant is advised that parking for contractor's vehicles and the storage of materials and deliveries associated with this development should take place within the site and not extend into within the public highway without authorisation from the highway authority. If necessary the applicant is advised to contact The Street Works Co-ordinator, Central Bedfordshire Highways, by contacting the Highways Helpdesk 0300 300 8301. Under the provisions of the Highways Act 1980 the developer may be liable for any damage caused to the public highway as a result of demolition/construction of the development hereby approved. |
| 4
)Best practical means shall be taken at all times to ensure that all vehicles leaving the development site during construction/demolition of the development are in a condition such as not emit dust or deposit mud, slurry or other debris on the highway, in particular efficient means shall be installed prior to commencement of the development and thereafter maintained and employed at all times during construction of the development of cleaning the wheels of all vehicles leaving the site.Best practical means shall be taken at all times to ensure that all vehicles leaving the development site during construction/demolition of the development are in a condition such as not emit dust or deposit mud, slurry or other debris on the highway, in particular efficient means shall be installed prior to commencement of the development and thereafter maintained and employed at all times during construction of the development of cleaning the wheels of all vehicles leaving the site. |
| 5
)The applicant is advised that parking for contractor's vehicles and the storage of materials and deliveries associated with this development should take
place within the site and not extend into within the public highway without authorisation from the highway authority. If necessary the applicant is
advised to contact The Street Works Co-ordinator, Central Bedfordshire Highways, by contacting the Highways Helpdesk 0300 300 8301. Under the
provisions of the Highways Act 1980 the developer may be liable for any damage caused to the public highway as a result of demolition/construction of
the development hereby approved.The applicant is advised that parking for contractor's vehicles and the storage of materials and deliveries associated with this development should take
place within the site and not extend into within the public highway without authorisation from the highway authority. If necessary the applicant is
advised to contact The Street Works Co-ordinator, Central Bedfordshire Highways, by contacting the Highways Helpdesk 0300 300 8301. Under the
provisions of the Highways Act 1980 the developer may be liable for any damage caused to the public highway as a result of demolition/construction of
the development hereby approved. |
| 6
)The applicant is advised that Bedfordshire Fire and Rescue Service have highlighted that the existing fire hydrant number 4288 is in the footpath immediately outside the proposed access to this site. The developer must ensure that this fire hydrant is not damaged or obstructed as a result of this development.The applicant is advised that Bedfordshire Fire and Rescue Service have highlighted that the existing fire hydrant number 4288 is in the footpath immediately outside the proposed access to this site. The developer must ensure that this fire hydrant is not damaged or obstructed as a result of this development. |
|
|---|