| Informative Notes: | | 1
)GDP Policy Informative Central Beds Local Plan
In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the Central Bedfordshire Local Plan and the National Planning Policy Framework (NPPF).GDP Policy Informative Central Beds Local Plan
In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the Central Bedfordshire Local Plan and the National Planning Policy Framework (NPPF). |
| 2
)This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority.This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority. |
| 3
)The applicant and the developer are advised that this permission is subject to a Unilateral Undertaking under Section 106 of the Town and Country Planning Act 1990.The applicant and the developer are advised that this permission is subject to a Unilateral Undertaking under Section 106 of the Town and Country Planning Act 1990. |
| 4
)Following an Appropriate Assessment and consultation with Natural England, it is considered that the application has been determined in accordance with Regulation 63 of the Conservation of Habitats and Species Regulations 2017Following an Appropriate Assessment and consultation with Natural England, it is considered that the application has been determined in accordance with Regulation 63 of the Conservation of Habitats and Species Regulations 2017 |
| 5
)In order to discharge condition No. 3, the applicant is advised of the following:
The base of the drive should be flat and/or berms installed to ensure full storage ability is achieved.
Permeable block paving should be laid to CIRIA C768 'Guidance on the construction of SuDS' guidelines. This guidance also stipulates following Interlay guidance.
The Council does not, and is not required to, adopt any SuDS feature. It is the responsibility of the applicant to ensure that the surface water drainage system, in its entirety, will be effectively maintained in the long-term. We therefore expect confirmation of the proposed arrangements for maintenance to be provided with the final detailed design, including the future maintenance and operational needs and the responsible bodies for undertaking maintenance (for all public and private drainage components).
The final detailed design including proposed standards of operation, construction, structural integrity and ongoing maintenance must be compliant with the 'Non-statutory technical standards for sustainable drainage systems' (March 2015, Ref: PB14308), 'Central Bedfordshire Sustainable Drainage Guidance' (Adopted April 2014, Updated May 2015), and recognised best practise including the Ciria SuDS Manual (2016, C753).In order to discharge condition No. 3, the applicant is advised of the following:
The base of the drive should be flat and/or berms installed to ensure full storage ability is achieved.
Permeable block paving should be laid to CIRIA C768 'Guidance on the construction of SuDS' guidelines. This guidance also stipulates following Interlay guidance.
The Council does not, and is not required to, adopt any SuDS feature. It is the responsibility of the applicant to ensure that the surface water drainage system, in its entirety, will be effectively maintained in the long-term. We therefore expect confirmation of the proposed arrangements for maintenance to be provided with the final detailed design, including the future maintenance and operational needs and the responsible bodies for undertaking maintenance (for all public and private drainage components).
The final detailed design including proposed standards of operation, construction, structural integrity and ongoing maintenance must be compliant with the 'Non-statutory technical standards for sustainable drainage systems' (March 2015, Ref: PB14308), 'Central Bedfordshire Sustainable Drainage Guidance' (Adopted April 2014, Updated May 2015), and recognised best practise including the Ciria SuDS Manual (2016, C753). |
|
|---|