| Details of Planning Application -
CB/22/00627/FULL |
| Application registered | Consultation period | Awaiting decision | Decided | Appeal | Appeal decided |
|
|---|
| Application Type: | Full Application |
|---|
| Date Received: | 15
/
02
/
2022 |
|---|
| Registration (Validation) Date: | 16
/
02
/
2022 |
|---|
| Consultation Start Date: | 16
/
02
/
2022 |
|---|
| Earliest Decision Date (Consultation Period Expires): | 23
/
03
/
2022 |
|---|
| Target Date for Decision: | 13
/
04
/
2022 |
|---|
| Location: | Rowan, Greenfield Road, Pulloxhill, Bedford, MK45 5EY |
|---|
| Parish Name: | Pulloxhill |
|---|
| Conservation Area: | Not available |
|---|
| Listed Building Grade: | Not available |
|---|
| Environmental Assessment: | Not available |
|---|
| Expected Decision Level: | Not available |
|---|
| Description: | Change of use of land from paddock to residential, relocation of site access and removal of old site access. |
|---|
| Case Officer: | Thomas Mead |
|---|
| Case Officer Tel: | 0300 300 4918 |
|---|
| Case Officer Email: | thomas.mead@centralbedfordshire.gov.uk |
|---|
| Status: | Decided |
|---|
| Agent: | Mr N Hansford |
|---|
| The Firs |
|---|
| 81 Station Road |
|---|
| Lower Stondon |
|---|
| SG16 6JN |
|---|
| Press Date: | No date |
|---|
| Site Notice Date: | No date |
|---|
| Neighbours | Responses Received:
0 |
|---|
| and Representatives: | In Favour:
0 |
|---|
| Representation Details | Against:
0 |
|---|
| Comments:
0 |
|---|
| Petitions Against:
0 |
|---|
| Petitions For:
0 |
|---|
| Officer Site Visit Date: | No date |
|---|
| Committee Site Visit Date: | No date |
|---|
| Committee Meeting Date: | No date |
|---|
| Decision Level: | Officer Delegated |
|---|
| Date Decision Made: | 19
/
10
/
2022 |
|---|
| Date Decision Despatched: | 19
/
10
/
2022 |
|---|
| Decision: | Full Application - Granted |
|---|
| Conditions or Reasons: | View Conditions or Reasons |
|---|
| Informative Notes: | | 1
)This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority.This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority. |
| 2
)GDP Policy Informative Central Beds Local Plan
In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the Central Bedfordshire Local Plan and the National Planning Policy Framework (NPPF).GDP Policy Informative Central Beds Local Plan
In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the Central Bedfordshire Local Plan and the National Planning Policy Framework (NPPF). |
| 3
)The applicant is advised that it is their responsibility to ensure that final ground conditions are fit for the end use of the site. If during any site investigation, excavation, engineering or construction works evidence of land contamination is identified, the applicant shall notify the Local Planning Authority without delay. Any land contamination identified shall be remediated to the satisfaction of the Local Planning Authority to ensure that the site is made suitable for its end use.The applicant is advised that it is their responsibility to ensure that final ground conditions are fit for the end use of the site. If during any site investigation, excavation, engineering or construction works evidence of land contamination is identified, the applicant shall notify the Local Planning Authority without delay. Any land contamination identified shall be remediated to the satisfaction of the Local Planning Authority to ensure that the site is made suitable for its end use. |
| 4
)The applicant is asked to avoid removing any hedgerow or planting during nesting season.The applicant is asked to avoid removing any hedgerow or planting during nesting season. |
|
|---|
| Appeal Received Date: | This case has no appeals against it |
|---|
| Planning Obligation Status: | Not available |
|---|