1. Return to Search Page >>2. Search Results >>3. Planning Application Detail
Details of Planning Application - CB/22/02755/FULL

Click on the Consultation link below for neighbour and statutory consultee information and to comment on this application. Ensure your opinions are received before the consultation closing date.


Application Details View Documents (opens in new window) Consultation
Application registeredConsultation periodAwaiting decisionDecidedAppealAppeal decided
Application Type:Full Application
Date Received:07 / 07 / 2022
Registration (Validation) Date:04 / 08 / 2022
Consultation Start Date:04 / 08 / 2022
Earliest Decision Date (Consultation Period Expires):18 / 10 / 2022
Target Date for Decision:29 / 09 / 2022
Location:Russell Farm, New Road, Maulden, Bedford, MK45 2BG
Parish Name:Maulden
Conservation Area:Not available
Listed Building Grade:Not available
Environmental Assessment:Not available
Expected Decision Level:Not available
Description:Construction of a detached building for office use, with associated access, parking and landscaping.
Case Officer:Janine Richardson
Case Officer Tel:0300 300 6983
Case Officer Email:janine.richardson@centralbedfordshire.gov.uk
Status:Decided
Agent:Mr R Harrington
First Floor
12 Church Square
Leighton Buzzard
Beds
LU7 1AE
Press Date:No date
Site Notice Date:31 / 08 / 2022
NeighboursResponses Received: 4
and Representatives:In Favour: 0
Representation DetailsAgainst: 4
Comments: 0
Petitions Against: 0
Petitions For: 0
Officer Site Visit Date:31/08/2022
Committee Site Visit Date:No date
Committee Meeting Date:No date
Decision Level:Officer Delegated
Date Decision Made:20 / 10 / 2022
Date Decision Despatched:20 / 10 / 2022
Decision:Full Application - Granted
Conditions or Reasons:View Conditions or Reasons
Informative Notes:
1 )The applicant should address the following points when submitting details to discharge Condition 2: Full set of calculations for each phase and in total, providing evidence of all surface water retained on site for the 1 in 100 (+40%CC+10% Urban Creep). Any exceedance should be shown with pathways, depths and velocity. Full drainage drawings showing all connections, control features, storage, inverts etc. and how it communicates with the development wide scheme. Culverting of existing watercourses will not be permitted. There should be a minimum 1m between the base of a soakage unit and the seasonal water table. Any watercourses within or adjacent to the site should be included in the maintenance and management plan, even if there is no discharge to them. This would be a riparian ownership issue but leaving it as such is no longer acceptable. Under Central Bedfordshire Council and IDB bylaws, any watercourse within or adjoining the site boundary will maintain a 9m development free easement (on the development side), unless otherwise agreed with the relevant drainage authority. This applies to all watercourses, where water is present for all or some of the year, including those not clearly stated on mapping, topography or planning documents. The connection of private surface water drainage systems to a highway system is not permitted. Permeable block paving should be laid to CIRIA C768 'Guidance on the construction of SuDS' guidelines. This guidance also stipulates following Interlay guidance. The Council does not, and is not required to, adopt any SuDS feature. It is the responsibility of the applicant to ensure that the surface water drainage system, in its entirety, will be effectively maintained in the long-term. We therefore expect confirmation of the proposed arrangements for maintenance to be provided with the final detailed design, including the future maintenance and operational needs and the responsible bodies for undertaking maintenance (for all public and private drainage components). The final detailed design including proposed standards of operation, construction, structural integrity and ongoing maintenance must be compliant with the 'Non-statutory technical standards for sustainable drainage systems' (March 2015, Ref: PB14308), 'Central Bedfordshire Sustainable Drainage Guidance' (Adopted April 2014, Updated May 2015), and recognised best practise including the Ciria SuDS Manual (2016, C753). Land drainage Consent under the Land Drainage Act 1991 must be secured to discharge surface water to an existing watercourse/ditch, and details of this provided with the full detailed design. An easement should be provided on the developable side of the watercourse to allow for access for maintenance, this should be 9m but may depend on the maintenance requirements considered appropriate.The applicant should address the following points when submitting details to discharge Condition 2: Full set of calculations for each phase and in total, providing evidence of all surface water retained on site for the 1 in 100 (+40%CC+10% Urban Creep). Any exceedance should be shown with pathways, depths and velocity. Full drainage drawings showing all connections, control features, storage, inverts etc. and how it communicates with the development wide scheme. Culverting of existing watercourses will not be permitted. There should be a minimum 1m between the base of a soakage unit and the seasonal water table. Any watercourses within or adjacent to the site should be included in the maintenance and management plan, even if there is no discharge to them. This would be a riparian ownership issue but leaving it as such is no longer acceptable. Under Central Bedfordshire Council and IDB bylaws, any watercourse within or adjoining the site boundary will maintain a 9m development free easement (on the development side), unless otherwise agreed with the relevant drainage authority. This applies to all watercourses, where water is present for all or some of the year, including those not clearly stated on mapping, topography or planning documents. The connection of private surface water drainage systems to a highway system is not permitted. Permeable block paving should be laid to CIRIA C768 'Guidance on the construction of SuDS' guidelines. This guidance also stipulates following Interlay guidance. The Council does not, and is not required to, adopt any SuDS feature. It is the responsibility of the applicant to ensure that the surface water drainage system, in its entirety, will be effectively maintained in the long-term. We therefore expect confirmation of the proposed arrangements for maintenance to be provided with the final detailed design, including the future maintenance and operational needs and the responsible bodies for undertaking maintenance (for all public and private drainage components). The final detailed design including proposed standards of operation, construction, structural integrity and ongoing maintenance must be compliant with the 'Non-statutory technical standards for sustainable drainage systems' (March 2015, Ref: PB14308), 'Central Bedfordshire Sustainable Drainage Guidance' (Adopted April 2014, Updated May 2015), and recognised best practise including the Ciria SuDS Manual (2016, C753). Land drainage Consent under the Land Drainage Act 1991 must be secured to discharge surface water to an existing watercourse/ditch, and details of this provided with the full detailed design. An easement should be provided on the developable side of the watercourse to allow for access for maintenance, this should be 9m but may depend on the maintenance requirements considered appropriate.
2 )The applicant is advised that in order to comply with Conditions 11 and 12 of this permission it will be necessary for the developer of the site to enter into an agreement with Central Bedfordshire Council as Highway Authority under Section 278 of the Highways Act 1980 to ensure the satisfactory completion of the access and associated road improvements. You are advised to contact the Highways Agreements Officer, Community Services, Central Bedfordshire Council, Priory House, Monks Walk, Chicksands, Shefford SG17 5TQ. E-mail highwaysagreements@centralbedfordshire.gov.uk The applicant is advised that no private surface water drainage system designed as part of a new development, will be allowed to enter any existing highway surface water drainage system. The applicant is advised that the requirements of the New Roads and Street Works Act 1991 will apply to any works undertaken within the limits of the existing public highway. Further details can be obtained by contacting The Street Works Co-ordinator, Central Bedfordshire Highways, by contacting the Highways Helpdesk 0300 300 8301. The applicant is advised that parking for contractor's vehicles and the storage of materials and deliveries associated with this development should take place within the site and not extend into within the public highway without authorisation from the highway authority. If necessary the applicant is advised to contact The Street Works Co-ordinator, Central Bedfordshire Highways, by contacting the Highways Helpdesk 0300 300 8301. Under the provisions of the Highways Act 1980 the developer may be liable for any damage caused to the public highway as a result of demolition/construction of the development hereby approved. Best practical means shall be taken at all times to ensure that all vehicles leaving the development site during construction/demolition of the development are in a condition such as not emit dust or deposit mud, slurry or other debris on the highway, in particular efficient means shall be installed prior to commencement of the development and thereafter maintained and employed at all times during construction of the development of cleaning the wheels of all vehicles leaving the site. The applicant is advised that in order to achieve the vision splays in condition 13 of the permission it may be necessary for vegetation overhanging the public highway to be removed. Prior to the commencement of work the applicant is advised to contact The Street Works Co-ordinator, Central Bedfordshire Highways, by contacting the Highways Helpdesk 0300 300 8301 to request the removal of the overhanging vegetation on the public highway. The applicant is advised that all cycle parking to be provided within the site shall be designed in accordance with the Central Bedfordshire Council's 'Cycle Parking Annexes July 2010'.The applicant is advised that in order to comply with Conditions 11 and 12 of this permission it will be necessary for the developer of the site to enter into an agreement with Central Bedfordshire Council as Highway Authority under Section 278 of the Highways Act 1980 to ensure the satisfactory completion of the access and associated road improvements. You are advised to contact the Highways Agreements Officer, Community Services, Central Bedfordshire Council, Priory House, Monks Walk, Chicksands, Shefford SG17 5TQ. E-mail highwaysagreements@centralbedfordshire.gov.uk The applicant is advised that no private surface water drainage system designed as part of a new development, will be allowed to enter any existing highway surface water drainage system. The applicant is advised that the requirements of the New Roads and Street Works Act 1991 will apply to any works undertaken within the limits of the existing public highway. Further details can be obtained by contacting The Street Works Co-ordinator, Central Bedfordshire Highways, by contacting the Highways Helpdesk 0300 300 8301. The applicant is advised that parking for contractor's vehicles and the storage of materials and deliveries associated with this development should take place within the site and not extend into within the public highway without authorisation from the highway authority. If necessary the applicant is advised to contact The Street Works Co-ordinator, Central Bedfordshire Highways, by contacting the Highways Helpdesk 0300 300 8301. Under the provisions of the Highways Act 1980 the developer may be liable for any damage caused to the public highway as a result of demolition/construction of the development hereby approved. Best practical means shall be taken at all times to ensure that all vehicles leaving the development site during construction/demolition of the development are in a condition such as not emit dust or deposit mud, slurry or other debris on the highway, in particular efficient means shall be installed prior to commencement of the development and thereafter maintained and employed at all times during construction of the development of cleaning the wheels of all vehicles leaving the site. The applicant is advised that in order to achieve the vision splays in condition 13 of the permission it may be necessary for vegetation overhanging the public highway to be removed. Prior to the commencement of work the applicant is advised to contact The Street Works Co-ordinator, Central Bedfordshire Highways, by contacting the Highways Helpdesk 0300 300 8301 to request the removal of the overhanging vegetation on the public highway. The applicant is advised that all cycle parking to be provided within the site shall be designed in accordance with the Central Bedfordshire Council's 'Cycle Parking Annexes July 2010'.
Appeal Received Date:This case has no appeals against it
Planning Obligation Status:Not available

Return to Search PageTop of Page