Details of Planning Application -
CB/23/01714/FULL |
Application registered | Consultation period | Awaiting decision | Decided | Appeal | Appeal decided |
|
---|
Application Type: | Full Application |
---|
Date Received: | 22
/
05
/
2023 |
---|
Registration (Validation) Date: | 22
/
06
/
2023 |
---|
Consultation Start Date: | 22
/
06
/
2023 |
---|
Earliest Decision Date (Consultation Period Expires): | 27
/
07
/
2023 |
---|
Target Date for Decision: | 17
/
08
/
2023 |
---|
Location: | 9 Regent Street, Stotfold, Hitchin, SG5 4ED |
---|
Parish Name: | Stotfold |
---|
Conservation Area: | Not available |
---|
Listed Building Grade: | Not available |
---|
Environmental Assessment: | Not available |
---|
Expected Decision Level: | Not available |
---|
Description: | Change of use from mixed C3/sui generis use (hot food take away), to C3 use, with first-floor side, single storey rear extension and external changes to the principal elevation. |
---|
Case Officer: | Julia Ward |
---|
Case Officer Tel: | 0300 300 4770 |
---|
Case Officer Email: | julia.ward@centralbedfordshire.gov.uk |
---|
Status: | Decided |
---|
Agent: | Mr J Clark |
---|
| 19 The Brambles |
---|
| Prospect Road |
---|
| St. Albans |
---|
| AL1 2DP |
---|
Press Date: | No date |
---|
Site Notice Date: | 06
/
07
/
2023 |
---|
Neighbours | Responses Received:
0 |
---|
and Representatives: | In Favour:
0 |
---|
Representation Details | Against:
0 |
---|
| Comments:
0 |
---|
| Petitions Against:
0 |
---|
| Petitions For:
0 |
---|
Officer Site Visit Date: | 18/07/2023 |
---|
Committee Site Visit Date: | No date |
---|
Committee Meeting Date: | No date |
---|
Decision Level: | Officer Delegated |
---|
Date Decision Made: | 09
/
08
/
2023 |
---|
Date Decision Despatched: | 10
/
08
/
2023 |
---|
Decision: | Full Application - Granted |
---|
Conditions or Reasons: | View Conditions or Reasons |
---|
Informative Notes: | 1
)GDP Policy Informative Central Beds Local Plan
In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the Central Bedfordshire Local Plan and the National Planning Policy Framework (NPPF).GDP Policy Informative Central Beds Local Plan
In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the Central Bedfordshire Local Plan and the National Planning Policy Framework (NPPF). |
2
)This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority.This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority. |
3
)The applicant is advised that parking for contractor's vehicles and the storage of materials associated with this development should take place within the site and not extend into within the public highway without authorisation from the highway authority. If necessary the applicant is advised to contact The Street Works Co-ordinator, Central Bedfordshire Highways, by contacting the Highways Helpdesk 0300 300 8301. Under the provisions of the Highways Act 1980 the developer may be liable for any damage caused to the public highway as a result of demolition/construction of the development hereby approved
The contractor and / or client are to ensure that any mud or building material debris such as sand, cement or concrete that is left on the public highway, or any mud arising from construction/demolition vehicular movement, shall be removed immediately and in the case of concrete, cement, mud or mortar not allowed to dry on the highwayThe applicant is advised that parking for contractor's vehicles and the storage of materials associated with this development should take place within the site and not extend into within the public highway without authorisation from the highway authority. If necessary the applicant is advised to contact The Street Works Co-ordinator, Central Bedfordshire Highways, by contacting the Highways Helpdesk 0300 300 8301. Under the provisions of the Highways Act 1980 the developer may be liable for any damage caused to the public highway as a result of demolition/construction of the development hereby approved
The contractor and / or client are to ensure that any mud or building material debris such as sand, cement or concrete that is left on the public highway, or any mud arising from construction/demolition vehicular movement, shall be removed immediately and in the case of concrete, cement, mud or mortar not allowed to dry on the highway |
4
)The applicant is advised where roofing work or timber treatment is to be undertaken it is the legal responsibility of the contractor to check for bats. If bats are found during the course of any work to buildings or trees where not previously anticipated, then works should immediately stop and Natural England notified for appropriate advice.The applicant is advised where roofing work or timber treatment is to be undertaken it is the legal responsibility of the contractor to check for bats. If bats are found during the course of any work to buildings or trees where not previously anticipated, then works should immediately stop and Natural England notified for appropriate advice. |
5
)You are advised to note the comments of the CBC Environmental Service Compliance Officer as set out:
There is a contribution to pay for the supply/delivery of the bins. A purchase order must be raised for the quantity of bins required and sent to Environmental Services quoting the relevant planning reference number.You are advised to note the comments of the CBC Environmental Service Compliance Officer as set out:
There is a contribution to pay for the supply/delivery of the bins. A purchase order must be raised for the quantity of bins required and sent to Environmental Services quoting the relevant planning reference number. |
|
---|
Appeal Received Date: | This case has no appeals against it |
---|
Planning Obligation Status: | Not available |
---|