| Details of Planning Application -
CB/23/01952/VOC |
| Application registered | Consultation period | Awaiting decision | Decided | Appeal | Appeal decided |
|
|---|
| Application Type: | Variation of Condition |
|---|
| Date Received: | 13
/
06
/
2023 |
|---|
| Registration (Validation) Date: | 14
/
06
/
2023 |
|---|
| Consultation Start Date: | 14
/
06
/
2023 |
|---|
| Earliest Decision Date (Consultation Period Expires): | 01
/
08
/
2024 |
|---|
| Target Date for Decision: | 09
/
08
/
2023 |
|---|
| Location: | Park Corner Farm, Dunton Lane, Biggleswade, SG18 8SH |
|---|
| Parish Name: | Biggleswade |
|---|
| Conservation Area: | Not available |
|---|
| Listed Building Grade: | Not available |
|---|
| Environmental Assessment: | Not available |
|---|
| Expected Decision Level: | Not available |
|---|
| Description: | Removal of condition number 2 of planning permission CB/22/04963/VOC (Erection of an agricultural building for the storage and grading of potatoes and storage of associated farming machinery) - Removal of original NatureSpace Certificate and issue of new Certificate |
|---|
| Case Officer: | Julia Ward |
|---|
| Case Officer Tel: | 0300 300 4770 |
|---|
| Case Officer Email: | julia.ward@centralbedfordshire.gov.uk |
|---|
| Status: | Decided |
|---|
| Agent: | J Struct |
|---|
| The Stables |
|---|
| Nether Hall |
|---|
| Moreton Ongar |
|---|
| CM5 0JA |
|---|
| Press Date: | No date |
|---|
| Site Notice Date: | 11
/
07
/
2024 |
|---|
| Neighbours | Responses Received:
0 |
|---|
| and Representatives: | In Favour:
0 |
|---|
| Representation Details | Against:
0 |
|---|
| Comments:
0 |
|---|
| Petitions Against:
0 |
|---|
| Petitions For:
0 |
|---|
| Officer Site Visit Date: | 07/03/2024 |
|---|
| Committee Site Visit Date: | No date |
|---|
| Committee Meeting Date: | No date |
|---|
| Decision Level: | Officer Delegated |
|---|
| Date Decision Made: | 28
/
11
/
2024 |
|---|
| Date Decision Despatched: | 29
/
11
/
2024 |
|---|
| Decision: | Variation of Condition - Granted |
|---|
| Conditions or Reasons: | View Conditions or Reasons |
|---|
| Informative Notes: | | 1
)GDP Policy Informative Central Beds Local Plan
In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the Central Bedfordshire Local Plan and the National Planning Policy Framework (NPPF).GDP Policy Informative Central Beds Local Plan
In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the Central Bedfordshire Local Plan and the National Planning Policy Framework (NPPF). |
| 2
)This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority.This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority. |
| 3
)The applicant should note that the Internal Drainage Board will not accept any tree or hedgerow planting within 9 metres of its easement.The applicant should note that the Internal Drainage Board will not accept any tree or hedgerow planting within 9 metres of its easement. |
| 4
)It is recommended that Naturespace Best Practice Principles are taken into account and implemented where possible and appropriate.It is recommended that Naturespace Best Practice Principles are taken into account and implemented where possible and appropriate. |
| 5
)It is essential to note that any works or activities whatsoever undertaken on site (including ground investigations, site preparatory works or ground clearance) prior to receipt of the written authorisation from the planning authority (which permits the development to proceed under the District Licence WML-OR112, or a "Further Licence") are not licensed under the great crested newt District Licence. Any such works or activities have no legal protection under the great crested District Licence and if offences against great crested newts are thereby committed then criminal investigation and prosecution by the police may follow.It is essential to note that any works or activities whatsoever undertaken on site (including ground investigations, site preparatory works or ground clearance) prior to receipt of the written authorisation from the planning authority (which permits the development to proceed under the District Licence WML-OR112, or a "Further Licence") are not licensed under the great crested newt District Licence. Any such works or activities have no legal protection under the great crested District Licence and if offences against great crested newts are thereby committed then criminal investigation and prosecution by the police may follow. |
|
|---|
| Appeal Received Date: | This case has no appeals against it |
|---|
| Planning Obligation Status: | Not available |
|---|