| Informative Notes: | | 1
)GDP Policy Informative Central Beds Local Plan
In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the Central Bedfordshire Local Plan and the National Planning Policy Framework (NPPF).GDP Policy Informative Central Beds Local Plan
In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the Central Bedfordshire Local Plan and the National Planning Policy Framework (NPPF). |
| 2
)This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority.This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority. |
| 3
)Highway Notes
The applicant is advised that in order to comply with those conditions related to works to, or effecting the public highway, including forming or revising the access junction and carrying out external works, it will be necessary for the developer of the site to undertake the necessary approvals process/es with Central Bedfordshire Council as Highway Authority to ensure the satisfactory completion of the access and associated road improvements. You are advised to contact the Highways Agreements Officer, Community Services, Central Bedfordshire Council, Priory House, Monks Walk, Chicksands, Shefford SG17 5TQ. E-mail highwaysagreements@centralbedfordshire.gov.uk
The applicant is advised that any planting within the public highway will be subject to the agreement of Central Bedfordshire Council as Highway Authority and will attract a commuted sum for ongoing maintenance.
The applicant is advised that no private surface water drainage system designed as part of a new development, will be allowed to enter any existing highway surface water drainage system.
The applicant is advised that the requirements of the New Roads and Street Works Act 1991 will apply to any works undertaken within the limits of the existing public highway. The applicant is further advised that no works associated with the CTMP should be carried out within the confines of the public highway without prior consent, in writing, of the Central Bedfordshire Council. Upon receipt of this Notice of Planning Approval, the applicant is advised to contact Central Bedfordshire Council Tel: 0300 300 8301 quoting the Planning Application number. This will enable the necessary consent and procedures under the Highways Act to be implemented.Highway Notes
The applicant is advised that in order to comply with those conditions related to works to, or effecting the public highway, including forming or revising the access junction and carrying out external works, it will be necessary for the developer of the site to undertake the necessary approvals process/es with Central Bedfordshire Council as Highway Authority to ensure the satisfactory completion of the access and associated road improvements. You are advised to contact the Highways Agreements Officer, Community Services, Central Bedfordshire Council, Priory House, Monks Walk, Chicksands, Shefford SG17 5TQ. E-mail highwaysagreements@centralbedfordshire.gov.uk
The applicant is advised that any planting within the public highway will be subject to the agreement of Central Bedfordshire Council as Highway Authority and will attract a commuted sum for ongoing maintenance.
The applicant is advised that no private surface water drainage system designed as part of a new development, will be allowed to enter any existing highway surface water drainage system.
The applicant is advised that the requirements of the New Roads and Street Works Act 1991 will apply to any works undertaken within the limits of the existing public highway. The applicant is further advised that no works associated with the CTMP should be carried out within the confines of the public highway without prior consent, in writing, of the Central Bedfordshire Council. Upon receipt of this Notice of Planning Approval, the applicant is advised to contact Central Bedfordshire Council Tel: 0300 300 8301 quoting the Planning Application number. This will enable the necessary consent and procedures under the Highways Act to be implemented. |
| 4
)Drainage Notes
1. Culverting of existing watercourses will not be permitted.
2. Any watercourses within or adjacent to the site should be included in the maintenance and management plan, even if there is no discharge to them. This would be a riparian ownership issue but leaving it as such is no longer acceptable.
3. Under Central Bedfordshire Council and IDB bylaws, any watercourse within or adjoining the site boundary will maintain a 9m development free easement (on the development side), unless otherwise agreed with the relevant drainage authority. This applies to all watercourses, where water is present for all or some of the year, including those not clearly stated on mapping, topography or planning documents.
4. The connection of private surface water drainage systems to a highway system is not permitted.
5. Permeable block paving should be laid to CIRIA C768 'Guidance on the construction of SuDS' guidelines. This guidance also stipulates following Interlay guidance.
6. The Council does not, and is not required to, adopt any SuDS feature. It is the responsibility of the applicant to ensure that the surface water drainage system, in its entirety, will be effectively maintained in the long-term. We therefore expect confirmation of the proposed arrangements for maintenance to be provided with the final detailed design, including the future maintenance and operational needs and the responsible bodies for undertaking maintenance (for all public and private drainage components).
7. The final detailed design including proposed standards of operation, construction, structural integrity and ongoing maintenance must be compliant with the 'Non-statutory technical standards for sustainable drainage systems' (March 2015, Ref: PB14308), 'Central Bedfordshire Sustainable Drainage Guidance' (Adopted April 2014, Updated May 2015), and recognised best practise including the Ciria SuDS Manual (2016, C753).Drainage Notes
1. Culverting of existing watercourses will not be permitted.
2. Any watercourses within or adjacent to the site should be included in the maintenance and management plan, even if there is no discharge to them. This would be a riparian ownership issue but leaving it as such is no longer acceptable.
3. Under Central Bedfordshire Council and IDB bylaws, any watercourse within or adjoining the site boundary will maintain a 9m development free easement (on the development side), unless otherwise agreed with the relevant drainage authority. This applies to all watercourses, where water is present for all or some of the year, including those not clearly stated on mapping, topography or planning documents.
4. The connection of private surface water drainage systems to a highway system is not permitted.
5. Permeable block paving should be laid to CIRIA C768 'Guidance on the construction of SuDS' guidelines. This guidance also stipulates following Interlay guidance.
6. The Council does not, and is not required to, adopt any SuDS feature. It is the responsibility of the applicant to ensure that the surface water drainage system, in its entirety, will be effectively maintained in the long-term. We therefore expect confirmation of the proposed arrangements for maintenance to be provided with the final detailed design, including the future maintenance and operational needs and the responsible bodies for undertaking maintenance (for all public and private drainage components).
7. The final detailed design including proposed standards of operation, construction, structural integrity and ongoing maintenance must be compliant with the 'Non-statutory technical standards for sustainable drainage systems' (March 2015, Ref: PB14308), 'Central Bedfordshire Sustainable Drainage Guidance' (Adopted April 2014, Updated May 2015), and recognised best practise including the Ciria SuDS Manual (2016, C753). |
|
|---|