Details of Planning Application - CB/23/03908/RM

Click on the Consultation link below for neighbour and statutory consultee information and to comment on this application. Ensure your opinions are received before the consultation closing date.


Application Details View Documents (opens in new window) Consultation
Application registeredConsultation periodAwaiting decisionDecidedAppealAppeal decided
Application Type:Reserved Matters
Date Received:05 / 12 / 2023
Registration (Validation) Date:08 / 12 / 2023
Consultation Start Date:08 / 12 / 2023
Earliest Decision Date (Consultation Period Expires):12 / 08 / 2024
Target Date for Decision:08 / 03 / 2024
Location:Vauxhall Aftersales Warehouse, Luton Road, Chalton, LU4 9TT
Parish Name:Chalton
Conservation Area:Not available
Listed Building Grade:Not available
Environmental Assessment:Not available
Expected Decision Level:Not available
Description:Reserved Matters: following Outline Application CB/21/05254/OUT amended by CB/23/01784/VOC (Variation of condition numbers 4, 13, 16, 20, 30 and 31 of planning permission CB/21/05254/OUT (Application on sites that cross local planning authority Boundaries: Outline Application: Hybrid planning application comprising: for the demolition of the existing buildings and the redevelopment of the site to provide flexible industrial, storage and distribution uses (Use Classes E(g)(iii)/B2/B8) and associated access, servicing, parking and landscaping (all matters reserved accept access) Full planning application for the proposed site accesses and landscaping along the site's frontage with Luton Road) Variation sought to increase floor area by 18,549sqm and increase height parameters by 1m.) Reserved Matters sought for full details of layout, scale, appearance and landscaping pursuant to Condition 14.
Case Officer:Peter Vosper
Case Officer Tel:0300 300 4157
Case Officer Email:peter.vosper@centralbedfordshire.gov.uk
Status:Decided
Agent:Mr J Finn
2 Kings Hill Avenue
Kings Hill
Kent
ME19 4AQ
Press Date:20 / 12 / 2023
Site Notice Date:05 / 01 / 2024
NeighboursResponses Received: 0
and Representatives:In Favour: 0
Representation DetailsAgainst: 0
Comments: 0
Petitions Against: 0
Petitions For: 0
Officer Site Visit Date:05/01/2024
Committee Site Visit Date:No date
Committee Meeting Date:No date
Decision Level:Officer Delegated
Date Decision Made:29 / 11 / 2024
Date Decision Despatched:29 / 11 / 2024
Decision:Reserved Matters- Granted
Conditions or Reasons:View Conditions or Reasons
Informative Notes:
1 )GDP Policy Informative Central Beds Local Plan In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the Central Bedfordshire Local Plan and the National Planning Policy Framework (NPPF).GDP Policy Informative Central Beds Local Plan In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the Central Bedfordshire Local Plan and the National Planning Policy Framework (NPPF).
2 )This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority.This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority.
3 )The applicant is advised that no private surface water drainage system designed as part of a new development will be allowed to enter any existing highway surface water drainage system.The applicant is advised that no private surface water drainage system designed as part of a new development will be allowed to enter any existing highway surface water drainage system.
4 )The applicant is advised that the requirements of the New Roads and Street Works Act 1991 will apply to any works undertaken within the limits of the existing public highway. Further details can be obtained by contacting the Streetworks Manager, Central Bedfordshire Council, by contacting the Highways Helpdesk 0300 300 8301.The applicant is advised that the requirements of the New Roads and Street Works Act 1991 will apply to any works undertaken within the limits of the existing public highway. Further details can be obtained by contacting the Streetworks Manager, Central Bedfordshire Council, by contacting the Highways Helpdesk 0300 300 8301.
5 )The applicant is advised that the storage of materials associated with the construction of this development should take place within the site and not extend into or within the public highway without authorisation from the highway authority. If necessary, the applicant should contact the Streetworks Manager, Central Bedfordshire Council, by contacting the Highways Helpdesk 0300 300 8301.The applicant is advised that the storage of materials associated with the construction of this development should take place within the site and not extend into or within the public highway without authorisation from the highway authority. If necessary, the applicant should contact the Streetworks Manager, Central Bedfordshire Council, by contacting the Highways Helpdesk 0300 300 8301.
6 )It is now a requirement that all multiple unit developments have gigabit-capable broadband services available. Whilst we remain agnostic about the supplier, developers must engage before the build begins. Confirmation or sight of a contractual agreement for this provision should be provided before development commences.It is now a requirement that all multiple unit developments have gigabit-capable broadband services available. Whilst we remain agnostic about the supplier, developers must engage before the build begins. Confirmation or sight of a contractual agreement for this provision should be provided before development commences.
7 )This planning permission is granted subject to a completed Unilateral Undertaking dated 2 October 2024 requiring a contribution of £5000 towards measures to restrict on-street parking if monitoring identifies such overspill parking on the adjacent or nearby public highways to the extent that it affects the operation and safety of the public highway.This planning permission is granted subject to a completed Unilateral Undertaking dated 2 October 2024 requiring a contribution of £5000 towards measures to restrict on-street parking if monitoring identifies such overspill parking on the adjacent or nearby public highways to the extent that it affects the operation and safety of the public highway.
Appeal Received Date:This case has no appeals against it
Planning Obligation Status:Not available