| Details of Planning Application -
CB/24/01905/FULL |
| Application registered | Consultation period | Awaiting decision | Decided | Appeal | Appeal decided |
|
|---|
| Application Type: | Full Application |
|---|
| Date Received: | 28
/
06
/
2024 |
|---|
| Registration (Validation) Date: | 01
/
07
/
2024 |
|---|
| Consultation Start Date: | 01
/
07
/
2024 |
|---|
| Earliest Decision Date (Consultation Period Expires): | 09
/
08
/
2024 |
|---|
| Target Date for Decision: | 26
/
08
/
2024 |
|---|
| Location: | 14 Grange Street, Clifton, Shefford, SG17 5EW |
|---|
| Parish Name: | Clifton |
|---|
| Conservation Area: | Clifton |
|---|
| Listed Building Grade: | Grade 2 |
|---|
| Environmental Assessment: | Not available |
|---|
| Expected Decision Level: | Not available |
|---|
| Description: | Replacement of, and alterations to, existing roof structure, including replacement timber wall plates, repair of damaged purlins, new rafters, new timber noggins, collars and ridge timbers, new roof covering and DPC membranes, new clay roof tiles, flashings to chimney stacks, weatherproofing to central valley, box gutter and re-pointing of roof verge cement to all four gables |
|---|
| Case Officer: | Julia Ward |
|---|
| Case Officer Tel: | 0300 300 4770 |
|---|
| Case Officer Email: | julia.ward@centralbedfordshire.gov.uk |
|---|
| Status: | Decided |
|---|
| Agent: | Mr M Tyler |
|---|
| 7 Ream Close |
|---|
| Eynesbury |
|---|
| St Neots |
|---|
| Eynesbury |
|---|
| PE19 2HE |
|---|
| Press Date: | 19
/
07
/
2024 |
|---|
| Site Notice Date: | 17
/
07
/
2024 |
|---|
| Neighbours | Responses Received:
0 |
|---|
| and Representatives: | In Favour:
0 |
|---|
| Representation Details | Against:
0 |
|---|
| Comments:
0 |
|---|
| Petitions Against:
0 |
|---|
| Petitions For:
0 |
|---|
| Officer Site Visit Date: | 17/07/2024 |
|---|
| Committee Site Visit Date: | No date |
|---|
| Committee Meeting Date: | No date |
|---|
| Decision Level: | Officer Delegated |
|---|
| Date Decision Made: | 14
/
08
/
2024 |
|---|
| Date Decision Despatched: | 14
/
08
/
2024 |
|---|
| Decision: | Full Application - Granted |
|---|
| Conditions or Reasons: | View Conditions or Reasons |
|---|
| Informative Notes: | | 1
)GDP Policy Informative Central Beds Local Plan
In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the Central Bedfordshire Local Plan and the National Planning Policy Framework (NPPF).GDP Policy Informative Central Beds Local Plan
In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the Central Bedfordshire Local Plan and the National Planning Policy Framework (NPPF). |
| 2
)This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority.This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority. |
| 3
)Please note that the unnumbered drawings submitted in connection with this application have been given unique numbers by the Local Planning Authority. The numbers can be sourced by examining the plans on the View a Planning Application pages of the Councils website www.centralbedfordshire.gov.uk.Please note that the unnumbered drawings submitted in connection with this application have been given unique numbers by the Local Planning Authority. The numbers can be sourced by examining the plans on the View a Planning Application pages of the Councils website www.centralbedfordshire.gov.uk. |
| 4
)The applicant is advised where roofing work or timber treatment is to be undertaken it is the legal responsibility of the contractor to check for bats. If bats are found during the course of any work to buildings or trees where not previously anticipated, then works should immediately stop and Natural England notified for appropriate advice.The applicant is advised where roofing work or timber treatment is to be undertaken it is the legal responsibility of the contractor to check for bats. If bats are found during the course of any work to buildings or trees where not previously anticipated, then works should immediately stop and Natural England notified for appropriate advice. |
|
|---|
| Appeal Received Date: | This case has no appeals against it |
|---|
| Planning Obligation Status: | Not available |
|---|