Conditions or Reasons for Planning Application - CB/23/00790/FULL
Conditions or Reasons:
1) The development hereby permitted shall begin not later than three years from the date of this permission.

Reason: To comply with Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2) The development hereby permitted shall not be carried out except in complete accordance with the details shown on the submitted plans, numbers: 2021/108/01, 2021/108/02, 2021/108/03, 2021/108/04, 2021/108/05, 2021/108/06/A, 2021/108/07/A and 2021/108/08.

Reason: To identify the approved plan/s and to avoid doubt.
3) Development shall not begin on the construction of the extensions until details of the junction of the proposed vehicular access with the highway have been submitted to and approved in writting by the Local Planning Authority. The junction shall be constructed in accordance with the approved details.

Reason: In order to minimise danger, obstruction and inconvenience to users of the highway and the premises.
4) The proposed vehicular access shall be surfaced in bituminous or other similar durable material (not loose aggregate) as may be approved in writing by the Local Planning Authority for a distance of 5m into the site, measured from the highway boundary within 6 months of the comp[letion of the development. Arrangements shall be made for surface water drainage from the site to be intercepted and disposed of separately so that it does not discharge into the highway.

Reason: To avoid the carriage of mud or other extraneous material or surface water from the site into the highway so as to safeguard the interest of highway safety.