Details of Planning Application - CB/21/02829/FULL

Click on the Consultation link below for neighbour and statutory consultee information and to comment on this application. Ensure your opinions are received before the consultation closing date.


Application Details View Documents (opens in new window) Consultation
Application registeredConsultation periodAwaiting decisionDecidedAppealAppeal decided
Application Type:Full Application
Date Received:16 / 06 / 2021
Registration (Validation) Date:12 / 07 / 2021
Consultation Start Date:12 / 07 / 2021
Earliest Decision Date (Consultation Period Expires):03 / 02 / 2022
Target Date for Decision:11 / 10 / 2021
Location:Land Adjacent to National Grid Sundon Substation, Water End Lane, Chalton, LU4 9UJ
Parish Name:Chalton, Toddington
Conservation Area:Not available
Listed Building Grade:Not available
Environmental Assessment:Not available
Expected Decision Level:Not available
Description:Battery storage development, components, new underground cabling, access tracks, GRP substation and associated works.
Case Officer:Caroline Macrdechian
Case Officer Tel:0300 300 5693
Case Officer Email:caroline.macrdechian@centralbedfordshire.gov.uk
Status:Decided
Agent:Not available
Press Date:21 / 07 / 2021
Site Notice Date:10 / 08 / 2021
NeighboursResponses Received: 1
and Representatives:In Favour: 0
Representation DetailsAgainst: 0
Comments: 1
Petitions Against: 0
Petitions For: 0
Officer Site Visit Date:10/08/2021
Committee Site Visit Date:No date
Committee Meeting Date:19 / 01 / 2022
Decision Level:Development Management Committee
Date Decision Made:19 / 01 / 2022
Date Decision Despatched:26 / 01 / 2022
Decision:Full Application - Granted
Conditions or Reasons:View Conditions or Reasons
Informative Notes:
1 )GDP Policy Informative Central Beds Local Plan In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the Central Bedfordshire Local Plan and the National Planning Policy Framework (NPPF).GDP Policy Informative Central Beds Local Plan In accordance with Article 35 (1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015, the reason for any condition above relates to the Policies as referred to in the Central Bedfordshire Local Plan and the National Planning Policy Framework (NPPF).
2 )This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority.This permission relates only to that required under the Town & Country Planning Acts and does not include any consent or approval under any other enactment or under the Building Regulations. Any other consent or approval which is necessary must be obtained from the appropriate authority.
3 )The applicant is advised that the requirements of the New Roads and Street Works Act 1991 will apply to any works undertaken within the limits of the existing public highway. Further details can be obtained from The Street Works Co-ordinator, Central Bedfordshire Highways, by contacting the Highways Helpdesk 0300 300 8301.The applicant is advised that the requirements of the New Roads and Street Works Act 1991 will apply to any works undertaken within the limits of the existing public highway. Further details can be obtained from The Street Works Co-ordinator, Central Bedfordshire Highways, by contacting the Highways Helpdesk 0300 300 8301.
4 )The applicant is reminded that, under the Conservation of Habitats and Species Regulations 2017 (as amended) and the Wildlife and Countryside Act 1981 (as amended), it is an offence to: deliberately capture, disturb, injure or kill great crested newts; damage or destroy a breeding or resting place; deliberately obstructing access to a resting or sheltering place. Planning consent for a development does not provide a defence against prosecution under these acts. Should great crested newts be found at any stages of the development works, then all works should cease, and Natural England should be contacted for advice.The applicant is reminded that, under the Conservation of Habitats and Species Regulations 2017 (as amended) and the Wildlife and Countryside Act 1981 (as amended), it is an offence to: deliberately capture, disturb, injure or kill great crested newts; damage or destroy a breeding or resting place; deliberately obstructing access to a resting or sheltering place. Planning consent for a development does not provide a defence against prosecution under these acts. Should great crested newts be found at any stages of the development works, then all works should cease, and Natural England should be contacted for advice.
5 )The applicant's attention is drawn to the response from Bedfordshire Fire and Rescue Service dated 17th January 2022. Prior to operation of the battery storage facility contact should be made with Bedfordshire Fire and Rescue Service to ensure appropriate safety measures are implemented to accord with the Regulatory Reform (Fire Safety) Order 2005 . The submitted Planning Fire Statement Outline (ref. TN-059) shall be updated as appropriate to accord with the regulations. Contact should also be made with Chalton Parish Council to discuss the fire safety requirements.The applicant's attention is drawn to the response from Bedfordshire Fire and Rescue Service dated 17th January 2022. Prior to operation of the battery storage facility contact should be made with Bedfordshire Fire and Rescue Service to ensure appropriate safety measures are implemented to accord with the Regulatory Reform (Fire Safety) Order 2005 . The submitted Planning Fire Statement Outline (ref. TN-059) shall be updated as appropriate to accord with the regulations. Contact should also be made with Chalton Parish Council to discuss the fire safety requirements.
Appeal Received Date:This case has no appeals against it
Planning Obligation Status:Not available